Skip to main content

Free RMP Exam Questions That Helps Candidates Pass

Free RMP practice questions for the PMI Risk Management Professional (PMI-RMP) exam, with answers and detailed explanations. Choose an answer, check it instantly and track your score as you go.

  • 80free questions
  • 245in full bank
  • 8pages
RMP Questions 1-10 of 80 free
0/10 answered · 0 correct

Choose an answer and click Check answer to see if you're right, with the full explanation.

Question 1

The project’s customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?

Correct answer: D

Explanation

The project manager should mitigate risks identified on the sensitivity analysis to ensure the P90 date is met. Sensitivity analysis helps identify the most critical risks that have the potential to impact the project's completion date. By mitigating these risks, the project manager can increase the likelihood of meeting the P90 date.

 According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, the P90 date is the date that has a 90% probability of being met or exceeded by the project completion1. The Monte Carlo analysis is a simul-ation technique that generates possible outcomes of the project schedule based on the probability distributions of the activity durations2. The sensitivity analysis is a technique that determines how different sources of uncertainty affect the project objectives, such as the completion date3. Therefore, the project manager should mitigate the risks identified on the sensitivity analysis, as they are the most likely to affect the P90 date. By reducing the uncertainty and variability of the project schedule, the project manager can increase the confidence level of meeting the P90 date.

[References: 1: PMI, Practice Standard for Project Risk Management, 2009, p. 91 2: PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Sixth Edition, 2017, p. 215 3: PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Sixth Edition, 2017, p. 403, , , ]

Question 2

A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?

Correct answer: C

Explanation

When a new risk manager is assigned to an ongoing project, their first step should be to review the existing risk management plan to understand the current policies, practices, and strategies in place.

 The new risk manager should first review the policies and practices that are outlined in the risk management plan, as this is the document that describes how risk management will be performed on the project. The risk management plan defines the roles and responsibilities, risk categories, risk appetite and thresholds, risk identification and analysis methods, risk response strategies, risk monitoring and reporting mechanisms, and risk governance structure for the project. The new risk manager should familiarize themselves with the risk management plan to understand the project environment and the expectations and requirements for risk management. The other options are not the first actions that the new risk manager should take. Reviewing potential next steps with the project team is a good practice, but it should be done after reviewing the risk management plan to ensure alignment and consistency. Reviewing the scope of work to determine the prescribed project methodology is not directly related to risk management, and it may not provide sufficient information about the project environment and the risk management approach. Reviewing the contract and determining the resources and project funding is part of the project initiation process, and it may not reflect the current status and issues of the project. References: 2, 3, 4

Question 3

 

One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.

Which risk response strategy is the program manager using in this scenario?

Correct answer: D

Explanation

 

In this scenario, the program manager is using the "Exploit" risk response strategy, which is aimed at ensuring that an opportunity is realized. By transferring all resources to the project and arranging for overtime pay, the program manager is taking proactive steps to ensure the project is completed early, thereby securing the large bonus. According to PMI, the "Exploit" strategy is used when the objective is to ensure that the opportunity is realized, typically involving actions that maximize the chances of achieving the desired outcome​.

Question 4

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

Correct answer: A

Explanation

The risk manager should perform a quantitative risk analysis to determine the potential impact of risks on the project's completion date. This will help in providing a more accurate project completion date to the customer, considering the risks and their potential effects on the project schedule.

 According to the PMI Risk Management Professional (PMI-RMP)® Examination Content Outline1, one of the tasks in the domain of Risk Analysis is to perform quantitative risk analysis using techniques such as Monte Carlo simul-ation, decision tree analysis, sensitivity analysis, etc., to quantify the possible outcomes for the project and their probabilities, and to evaluate the cost and schedule impacts of risks1. In this scenario, the risk manager should perform a quantitative risk analysis and update the results, because the project costs have increased significantly and the customer has imposed a strict deadline for the project completion. A quantitative risk analysis will help the risk manager to estimate the probability of meeting the project objectives, such as cost and schedule, and to determine the appropriate contingency reserves for the project. A quantitative risk analysis will also provide more accurate and reliable information for the customer and the project team, and will support the risk response planning process2. References: 1: PMI Risk Management Professional (PMI-RMP)® Examination Content Outline, page 92: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, pages 431-432.

Question 5

A major data center initiative involves performing a sensitivity analysis to determine the center's required amount of disaster recovery. Several key stakeholders are in disagreement about which level of disaster recovery is required. The lessons learned disaster recovery plans, and the difference for this data center is its geographical location and unique climate requirements. The database includes examples from previous similar initiatives, as well as the competitor's advertised plans.

What should the risk manager do to quantify the risk?

Correct answer: D

Explanation

The Delphi technique is a structured communication process designed to build consensus among a group of experts and stakeholders when opinions differ and a quantitative assessment is needed. It uses rounds of anonymous input and feedback, allowing experts to refine their views based on others' anonymous contributions. This approach is especially useful when stakeholders are in disagreement and objective quantification of risk is required.

PMBOK® Guide Extract:

“The Delphi technique is a way to reach a consensus of experts. Project risk experts participate in this technique anonymously. A facilitator uses a questionnaire to solicit ideas about the important project risks. The responses are summarized and recirculated to the experts for further comment. Consensus may be reached in a few rounds of this process. The Delphi technique helps reduce bias in the data and keeps any one person from having undue influence on the outcome.”

— PMBOK® Guide, 6th Edition, Section 11.2.2.4

ISO 31000 Reference:

“Facilitated workshops and expert elicitation techniques, such as the Delphi method, can help achieve an objective and consensus-based understanding of complex risks.”

— ISO 31000:2018, Section 6.4.2

In this scenario, since the stakeholders are in disagreement and the project involves complex, location-specific disaster recovery requirements, the Delphi technique (Option D) is the officially recommended approach to achieving consensus and quantifying risk.

[References:, PMI PMBOK® Guide, 6th Edition, Section 11.2.2.4, Practice Standard for Project Risk Management, PMI, ISO 31000:2018, Section 6.4.2, , , ]

Question 6

A highly complex project is about to start Considering that many changes and new information will arise as the work moves forward, key stakeholders are anxious about not addressing risks on time

What should the risk manager do in this situation?

Correct answer: D

Explanation

In highly complex projects where changes and new information are expected to arise continually, it's crucial to implement a dynamic and frequent risk management process. This approach ensures that risks are identified, assessed, and addressed promptly as they emerge throughout the project lifecycle. By regularly updating risk assessments and involving key stakeholders in ongoing risk discussions, the project team can maintain a proactive stance, effectively mitigating potential issues before they escalate. This continuous engagement fosters transparency and reduces stakeholder anxiety by demonstrating a commitment to managing uncertainties actively.

PMI Risk Management Study Guide References:

The importance of a dynamic risk management process is emphasized in the PMI-RMP Exam Preparation Study Guide, which highlights the need for continuous risk assessment and stakeholder engagement to adapt to evolving project conditions.

Question 7

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

Select 3 answers.

Correct answer: B, D, E

Explanation

In qualitative risk analysis, in addition to probability and impact, other factors can be used to refine the risk prioritization. Three valid factors to consider are:

1. Urgency: This refers to the timeframe within which a risk is likely to occur or the speed at which it might impact the project. High urgency risks require quicker responses, making them more critical in prioritization.

2. Proximity: This factor considers the time until the risk might affect the project. Risks that are likely to occur sooner may be given higher priority because they may require immediate attention.

3. Detectability: This assesses how easily the presence or impact of a risk can be identified. Risks that are hard to detect might be more dangerous and may require more resources to monitor and manage.

These factors are mentioned in PMI's guidelines for qualitative risk analysis as they provide a more nuanced view of risks beyond just probability and impact, allowing for more targeted and effective risk management strategies​.

 

 

Question 8

A risk manager wants to determine what risk has the biggest impact on project cost. The risk manager identified three risks, which could occur in different phases of the project.

What should the risk manager do first to understand the impact on project cost?

Correct answer: B

Question 9

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

Correct answer: B

Explanation

According to the PMI Risk Management Professional (PMI-RMP)® Examination Content Outline1, one of the tasks in the domain of Risk Response is to execute the approved risk response plan in accordance with project guidelines and procedures1. A risk response plan is a component of the project management plan that describes the agreed-upon and funded actions to address the project risks, both positive and negative2. In this scenario, the risk manager should execute the approved risk response plan to deal with the new risk that appears when requesting fuel from another supplier, which will cause delays with several other projects. The risk response plan should have been developed and approved during the risk response planning process, which involves selecting and prioritizing the appropriate risk strategies and actions for each risk3. The risk response plan should also be aligned with the project guidelines and procedures, which are the rules and directions that define the project’s scope, schedule, cost, quality, and other aspects4. The risk manager should not escalate the problem to the project sponsors, because that is not a risk response strategy, but rather a way to seek higher-level authority or support for a risk that is outside the project’s scope or influence5. The risk manager should not negotiate with the supplier to resolve the problem, because that is not a risk response strategy, but rather a procurement management technique that involves reaching a mutually acceptable agreement with the supplier on the terms and conditions of the contract6. The risk manager should not assign a team member to update the issue log, because that is not a risk response strategy, but rather a risk monitoring and reporting technique that involves tracking and documenting the issues that have occurred or are currently affecting the project7. References: 1: PMI Risk Management Professional (PMI-RMP)® Examination Content Outline, page 102: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, page 4143: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, page 4404: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, page 385: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, page 4376: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, page 4717: What Is an Issue Log? Templates & Tips7.

Question 10

A project team is discussing which risk requires more attention and resources for response planning. The team evaluated the schedule to determine which activity had the greatest impact on the project's total duration.

After analyzing the quantitative analysis results, which activity should the team pay more attention to?

Use the chart for the analysis.

Correct answer: A
0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free RMP questions practiced · - overall accuracy

Want the full RMP question bank?

Unlock all 245 questions with mock exam, explanations for every option and domain-level analytics.

Page 1 of 8 · Questions 1-10 of 80 free

Our free RMP exam questions sample is your personalized diagnostic tool. Get an instant, honest snapshot of your readiness for the PMI Risk Management Professional (PMI-RMP) exam and identify the specific topics that need your focus.

What You Get with Full Access:

Complete Question Bank

Mock Exam (Same real exam time and questions)

Smart Performance Dashboard

Identify Weak Spots

Verified Answer & Explanations

Unlimited Reattempts

Mobile-Friendly Study

Regular Content Updates

RMP Complete Package

Choose a plan and prepare with realistic RMP test questions designed to mirror test-day conditions. Every plan includes a full PMI Risk Management Professional (PMI-RMP) practice exam questions, a timed exam simulator, performance tracking, detailed answer explanations, and the ability to reattempt questions to improve accuracy and confidence.

PracticeTestMaster is an independent exam prep provider. RMP is the property of PMI.

Full access

Unlock all 245 RMP questions

You're practicing 80 free questions. Paid plans add:

  • 165 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your RMP progress

Questions answered0
Accuracy-

Saved on this device.

RMP exam overview

Exam
PMI Risk Management Professional (PMI-RMP)
Code
RMP
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 245 questionsFrom $19.99
Unlock