Skip to main content

Free RMP Exam Questions That Helps Candidates Pass - Page 6

RMP Questions 51-60 of 80 free
0/10 answered · 0 correct

Choose an answer and click Check answer to see if you're right, with the full explanation.

Question 51

A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.

Which technique should the risk manager use in this situation?

Correct answer: B

Explanation

The risk manager should use the Delphi method in this situation, as this is a technique that can help resolve differences among experts and reach a consensus on the identified risks and their characteristics. The Delphi method is a tool used to make quick decisions with consensus. This technique consists of sending several sets of anonymous questions to each expert. This is followed by a group discussion after every round. The Delphi method can help the risk manager to solicit the opinions of all experts without revealing their identities. This way, the experts can express their views freely and honestly, without being influenced or intimidated by others. The Delphi method can also reduce personal bias, ego, or emotional conflict among the participants. The risk manager can use the results of the Delphi method to create a list of potential risks and their causes, effects, and probabilities. The other options are not appropriate techniques for the risk manager to use in this situation. Brainstorming is a technique that can help generate ideas and identify risks, but it may not be effective in resolving differences among experts, as it involves open and spontaneous discussion. Focus group is a technique that can help collect requirements and opinions from stakeholders, but it may not be suitable for resolving technical disagreements among experts, as it involves a moderated and structured discussion. Checklist analysis is a technique that can help identify risks based on historical information and lessons learned, but it may not be helpful in resolving differences among experts, as it involves a predefined list of potential risks. References: 3, 4, 5

Question 52

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Correct answer: A

Explanation

When closing risks as part of the closing process, it is important to update the lessons learned document. This document captures the knowledge and experience gained during the project and can be valuable for future projects.

 Lessons learned is a document that captures the knowledge gained from the project and can help improve the performance of future projects. It is one of the outputs of the project closure process and should include information on the project risks, issues, and responses. Lessons learned can help identify the best practices and lessons to be applied or avoided in similar projects. Updating the lessons learned document is an important part of closing the risks as it can provide valuable insights for risk management. References: PMI, Project Risk Management, 2nd edition, 2019, p. 97-981

Question 53

In reviewing the team's identified project risks, a project manager identified an opportunity to assign more resources to ensure the company receives the project's incentive payment for early completion.

In implementing this plan, which response should the risk manager use?

Correct answer: A

Explanation

The appropriate risk response for an opportunity where the project team plans to assign more resources to ensure the company receives an incentive payment for early completion is to "Exploit." Exploiting a risk means taking action to ensure that the opportunity is realized, particularly when it is an opportunity with a positive impact that the project team wants to guarantee. In this case, the opportunity to complete the project early and receive an incentive payment aligns with the definition of an "Exploit" response, as it is an active approach to maximize the benefits from the opportunity.

 

 

Question 54

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.

What should the risk manager do?

Correct answer: B

Explanation

To address the lack of risk management buy-in from the project team, the risk manager should organize risk engagement activities, such as workshops. These activities can help create awareness of the importance of risk management and motivate the team to take their risk management responsibilities seriously.

 Risk engagement is the process of involving stakeholders in risk management activities, such as identifying, analyzing, prioritizing, and responding to risks. Risk engagement activities are designed to motivate and influence the project team and other stakeholders to take their risk management responsibilities seriously and to understand the benefits of risk management for the project’s success. Risk engagement activities can include workshops, games, simul-ations, brainstorming sessions, surveys, interviews, and other interactive methods. Risk engagement activities can help to create a positive risk culture, improve communication and collaboration, increase risk awareness and ownership, and enhance risk management skills and knowledge. References: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications1, page 9; Mastering PMI-RMP Domains, Tasks, and Enablers for Effective Risk2

Question 55

A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach.

Which risk identification approach should the risk manager use to achieve this goal?

Correct answer: D

Explanation

Assumptions and constraints analysis focuses on reviewing project documents (scope baseline, estimates, etc.) to determine what is assumed or constrained, and then assesses the risks arising from those assumptions and constraints. The PMBOK® Guide describes:

"Assumptions and constraints analysis explores the validity of project assumptions and constraints, as documented in scope baselines and estimates, and evaluates their potential impact on project objectives."

— PMBOK® Guide, 6th Edition, Section 11.2.2.2

[References:, PMBOK® Guide, 6th Edition, Section 11.2.2.2, , ]

Question 56

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

Correct answer: D

Explanation

The first element the risk owner should look for in the response plan is to verify that due dates for the actions have been identified. This ensures that risk mitigation actions are timely and can be effectively monitored.

 After identifying the risks and assigning risk owners, the next step is to develop risk response plans that describe how to address each risk. The first element that the risk owner should look for in the response plan is the due date for the actions that are required to implement the response. The due date is important because it helps to prioritize the risk response activities, monitor the progress of the risk response, and ensure that the response is executed in a timely manner. The due date also helps to align the risk response with the project schedule and avoid any delays or conflicts. The other elements, such as the probability of a secondary risk, the impact on the quality of the components, and the relationship with the critical path, are also relevant for the risk response plan, but they are not the first element that the risk owner should look for. References: PMI, 2017. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Newtown Square, PA: Project Management Institute, Inc., pp. 407-4081

Question 57

A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project's technical debt and meet the project deadline.

What should the risk manager advise the project manager to do to address this situation?

Correct answer: B

Explanation

The risk manager should advise the project manager to hire additional developers as soon as project metrics indicate that the risk of delay is materializing. This approach ensures that the response is timely and directly tied to the project’s actual performance, allowing for better resource management and minimizing unnecessary costs. This aligns with PMI's risk management principles, which advocate for the timely execution of risk responses based on objective data and metrics​.

 

 

Question 58

Some engineers are completing an activity that will alert the project team if there is a risk of requiring additional effort to complete the project. What should the risk manager do in case the trigger arises?

Correct answer: A

Explanation

A contingency plan is pre-planned for specific risk triggers. When the trigger is observed, the contingency plan should be activated as specified. PMBOK® Guide states:

"If a risk trigger occurs, the corresponding contingency plan or fallback plan should be implemented as documented in the risk response plan."

— PMBOK® Guide, 6th Edition, Section 11.6

[References:, PMBOK® Guide, 6th Edition, Section 11.6, ]

Question 59

A company is preparing a formal response to bid for an infrastructure engineering, procurement, and construction project. When should a risk register be developed to identify risks?

Correct answer: C

Explanation

A risk register should be developed before submitting a formal bid response to help the company understand the project's risk profile and account for potential risks in their proposal. This allows the company to make informed decisions about cost, schedule, and resources. (Reference: Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Section 11.2)

A risk register is a document that is used as a risk management tool to identify potential setbacks within a project. A risk register is typically created at the start of a project (before it begins), and is regularly referenced and updated throughout the life of a project through deliberate risk monitoring and control1. A risk register is an important component of any successful risk management process and helps mitigate potential project delays that could arise. A risk register is shared with project stakeholders to ensure information is stored in one accessible place2. A risk register also helps to establish a hierarchy of risks, starting with the most impactful. The goal should be to have a path to mitigating those risks, reducing the harm they cause, or eliminating them. The register should also outline what’s considered an acceptable level of risk and how to set up insurance to help offset the impacts3. Therefore, a risk register should be developed before a formal bid response is provided to the client to gain a greater understanding of the project’s risk profile. This will help to estimate the project costs, schedule, and scope more accurately and realistically, as well as to identify the contingency plans and reserves needed to deal with the potential risks. Developing a risk register during the project execution phase, when a client project kick-off meeting is held, or after a project budget is set up with a purchase order are all too late to effectively identify and manage the risks that could affect the project success. References: 2, 3, 1, 4

Question 60

it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.

Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?

Correct answer: B

Explanation

The Project Evaluation and Review Technique (PERT) is a statistical tool used in project management to estimate the duration of tasks by considering uncertainty and variability. PERT employs a weighted average of three time estimates:

Optimistic (O): The shortest time in which the task can be completed (3 hours).

Most Likely (M): The best estimate of the time required under normal conditions (5 hours).

Pessimistic (P): The longest time the task might take, assuming potential issues (7 hours).

PMI Risk Management Study Guide References:

The PMI-RMP Exam Preparation Study Guide outlines the PERT formula and its application in estimating task durations, highlighting its effectiveness in incorporating uncertainty into project schedules.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free RMP questions practiced · - overall accuracy

Want the full RMP question bank?

Unlock all 245 questions with mock exam, explanations for every option and domain-level analytics.

Page 6 of 8 · Questions 51-60 of 80 free

PracticeTestMaster is an independent exam prep provider. RMP is the property of PMI.

Full access

Unlock all 245 RMP questions

You're practicing 80 free questions. Paid plans add:

  • 165 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your RMP progress

Questions answered0
Accuracy-

Saved on this device.

RMP exam overview

Exam
PMI Risk Management Professional (PMI-RMP)
Code
RMP
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 245 questionsFrom $19.99
Unlock