RMP Questions 71-80 of 80 free
0/10 answered · 0 correct

Choose an answer and click Check answer to see if you're right, with the full explanation.

Question 71

During a complex infrastructure project, the team successfully mitigated a risk related to equipment failure. However, the mitigation strategy resulted in a secondary issue due to the use of alternative machinery.

What should the risk manager do?

Correct answer: D

Explanation

The correct answer is D. Update the project stakeholders and seek their input on the resulting secondary risk.

This question describes a secondary risk, which is a new risk that arises as a direct result of implementing a risk response. The original equipment-failure risk was successfully mitigated, but the use of alternative machinery introduced another issue. In standard risk management practice, once a secondary risk is identified, it must be documented, assessed, communicated, and managed through the normal risk process. Because this new risk can affect project objectives and may require additional response planning, relevant stakeholders should be informed and involved in determining the best course of action.

Option D is the best answer because secondary risks should not be ignored or delayed unnecessarily. Stakeholder input is important to evaluate the impact of the new issue, determine acceptable response options, and align decisions with project priorities and risk thresholds.

Why the other options are incorrect:

    A. Assign a risk owner and develop the risk mitigations at the next scheduled risk meeting.Assigning an owner and planning mitigation are valid activities, but waiting until the next scheduled meeting may delay needed action. The question asks what the risk manager should do now after identifying the secondary risk. Immediate stakeholder communication is more appropriate.

    B. Continue with the project as the risk identified is inconsequential.The scenario does not support the conclusion that the secondary risk is insignificant. Assuming it is inconsequential without analysis would be poor risk practice.

    C. Assign risk responsibility to the project manager to determine how to proceed.Risk responsibility should be assigned to the most appropriate owner, not automatically to the project manager. Also, the correct first step is broader communication and engagement around the newly emerged secondary risk.

Best-practice reasoning:

Secondary risks are a recognized output of risk response actions. They should be captured and processed like any other identified risk. Transparent stakeholder communication is especially important when a response action creates new uncertainty.

Reference-aligned basis:

This answer is consistent with standard risk management guidance that emphasizes:

    risk responses can generate secondary risks,

    newly identified risks should be communicated and assessed,

    stakeholders should be engaged when new risks emerge from implemented responses.

[References:, PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Implement Risk Responses and Monitor Risks, PMI, Practice Standard for Project Risk Management, ISO 31000, communication, consultation, and risk treatment principles, ============]

Question 72

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Correct answer: C

Explanation

 

Biases during risk identification can skew the perception of potential risks and their triggers. To mitigate this, the risk manager should rely on objective data, such as published operational experience reports, which provide historical data and insights into what has triggered risks in similar projects. This approach reduces the influence of biases and ensures that risk identification is based on empirical evidence rather than subjective judgments. Using these reports aligns with best practices in risk management, where decisions are data-driven and supported by documented experiences, reducing the likelihood of overlooking critical risk triggers​​.

 

Question 73

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

Correct answer: D

Explanation

According to the PMBOK Guide, the risk owner is the person assigned the responsibility of monitoring the risk and implementing the risk response plan. The risk owner should be involved in the risk response execution and evaluation, and should communicate the results and outcomes to the relevant stakeholders. In the case of a data breach, the risk owner should coordinate a response with the risk manager and other parties involved, such as the security team, the legal team, the customer service team, and the senior management. The risk owner should also report the status of the risk and the effectiveness of the response plan to the risk manager. The risk manager should oversee the risk response process and ensure that the risk is handled appropriately and in alignment with the project objectives and stakeholder expectations. References: = PMBOK Guide, 6th edition, pages 452-453; The Standard for Risk Management in Portfolios, Programs, and Projects, page 79.

Question 74

A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.

What is an effect of adding the correlation to the model?

Correct answer: C

Explanation

Adding correlation to the model accounts for the relationship between activities, which can result in increased variability in the model's outcomes. This will increase the standard deviation, which is a measure of the uncertainty in the model.

 According to the PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1, an effect of adding the correlation to the Monte Carlo schedule risk analysis model is that it increases the standard deviation of the model. This is because:

Correlation is the statistical relationship between two or more variables. In a schedule risk analysis, correlation can be used to model the dependency between the durations of different activities. For example, if two activities are positively correlated, it means that if one activity takes longer than expected, the other activity is also likely to take longer than expected. Conversely, if two activities are negatively correlated, it means that if one activity takes longer than expected, the other activity is likely to take shorter than expected.

A Monte Carlo schedule risk analysis is a simul-ation technique that uses random values for uncertain variables, such as activity durations, to generate possible outcomes for the project schedule. The simul-ation is repeated many times to produce a probability distribution of the project completion date and duration. The standard deviation is a measure of the variability or dispersion of the distribution. A higher standard deviation means that the distribution is more spread out and less predictable.

Adding correlation to the Monte Carlo schedule risk analysis model increases the standard deviation of the model because it introduces more variability and uncertainty to the simul-ation. Correlated activities can have a cumulative effect on the project schedule, either positively or negatively, depending on the direction and strength of the correlation. This can result in more extreme outcomes for the project completion date and duration, which increase the spread of the distribution and the standard deviation.

PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1

Risk Management Professional (PMI-RMP)® Exam Cert Guide2

Question 75

A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.

Given the project's complexity, what should the risk manager do?

Correct answer: C

Explanation

For complex projects, facilitating a risk identification exercise with key stakeholders ensures thoroughness. PMBOK® Guide recommends:

"Formal risk identification with all relevant stakeholders is critical, particularly in complex projects, to ensure all potential risks are recognized."

— PMBOK® Guide, 6th Edition, Section 11.2

[References:, PMBOK® Guide, 6th Edition, Section 11.2, ]

Question 76

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

Correct answer: C

Explanation

 A decision tree analysis is a tool that helps to evaluate and select the best option among different alternatives based on costs and probabilities. A decision tree analysis uses a graphical representation of a decision problem, where each node represents a decision point, a chance event, or an outcome. The branches of the tree show the possible choices, events, or consequences that can occur at each node. The end nodes of the tree show the expected value or payoff of each option, which is calculated by multiplying the probability and the cost or benefit of each outcome. A decision tree analysis can help to compare the expected values of different options and choose the one that maximizes the benefit or minimizes the cost1. A decision tree analysis can also help to incorporate uncertainty and risk into the decision making process, as it shows the range of possible outcomes and their likelihoods2. Therefore, the project manager should perform a decision tree analysis to evaluate and select the best option based on costs and probabilities for a mega facility development project. Performing a FMECA fault tree analysis, conducting a sensitivity analysis, or conducting an analytic hierarchy process are not the best options to evaluate and select the best option based on costs and probabilities. A FMECA fault tree analysis is a tool that helps to identify and analyze the potential causes and effects of failures in a system or process. It uses a graphical representation of a failure event, where each node represents a basic or intermediate event that contributes to the failure. The branches of the tree show the logical relationships between the events, using AND or OR gates. A FMECA fault tree analysis can help to calculate the probability and severity of failures, as well as to prioritize and mitigate the risks3. However, a FMECA fault tree analysis does not help to compare different options or alternatives, as it focuses on a single failure scenario. Conducting a sensitivity analysis is a tool that helps to measure how the uncertainty in the input variables of a model affects the output or outcome of the model. It uses a graphical or numerical representation of the relationship between the input and output variables, showing how the output changes when the input changes. A sensitivity analysis can help to identify the most critical or influential variables, as well as to test the robustness or reliability of the model4. However, a sensitivity analysis does not help to compare different options or alternatives, as it focuses on a single model or option. Conducting an analytic hierarchy process is a tool that helps to evaluate and select the best option among different alternatives based on multiple criteria. It uses a mathematical method of pairwise comparison, where each alternative is compared to each other in terms of each criterion. The results of the comparisons are then aggregated into a matrix, which shows the relative importance or preference of each alternative. An analytic hierarchy process can help to rank the alternatives and choose the one that best satisfies the criteria5. However, an analytic hierarchy process does not help to incorporate costs and probabilities into the decision making process, as it relies on subjective judgments and preferences. References: 1, 2, 3, 4, 5.

A decision tree analysis is a quantitative risk analysis technique that helps evaluate and select the best option based on costs and probabilities. It visually represents different decision paths and their associated probabilities, allowing the project manager to compare and select the most appropriate option for the project.

Question 77

A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.

What should the risk manager consider?

Correct answer: D

Explanation

 According to the PMI-RMP Exam Content Outline1, one of the tasks in the domain of risk identification is to “review project documents, assumptions, and constraints, and understand the project environment and organizational factors to identify risks”. The project charter, work breakdown structure (WBS), and scope statement are essential project documents that provide information about the project objectives, deliverables, requirements, assumptions, and constraints. Without these elements, the risk manager will have difficulty identifying and evaluating the risks that may affect the project. Therefore, the best answer is D. References: 1: PMI-RMP Exam Content Outline, page 7.

Question 78

Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.

What will help calculate the impact?

Correct answer: A

Explanation

Risk impact assessment involves calculating the impact of identified risks. Risk analysis is the process of examining, estimating, and evaluating the impact of risks, which helps in calculating the impact (Reference: PMBOK Guide, 6th Edition, p. 417)

Risk analysis is the process of assessing the likelihood and impact of the identified risks on the program objectives. It helps to calculate the impact of the risks by using qualitative or quantitative methods. Risk analysis can provide useful information for risk prioritization, risk response planning, and risk reporting. References: PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 67; PMI, The Standard for Program Management, Fourth Edition, 2017, p. 113.

Question 79

As a project approached completion, a risk manager conducted a risk response audit and verified the effectiveness of risk responses. What should the risk manager do next?

Correct answer: A

Explanation

 

After verifying the effectiveness of the risk responses, the next step is to close out the risk response actions and communicate the results to relevant stakeholders. This ensures that the project team and stakeholders are aware of how risks have been managed and that any lessons learned can be applied to future projects. This aligns with PMI's emphasis on communication and documentation in risk management to ensure transparency and continuous improvement​.

 

Question 80

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Correct answer: A

Explanation

According to the PMI Risk Management Professional (PMI-RMP)® Handbook1, one of the domains of the PMI-RMP exam is Risk Monitoring and Reporting, which involves tracking identified risks, monitoring residual risks, identifying new risks, executing risk response plans, and evaluating risk process effectiveness throughout the project1. The risk manager of the related project should have reformed the risk monitoring and closing process properly to ensure that the contingency budget is only used for the intended risks and not for other purposes. The risk manager should have also communicated the status and outcomes of the risk activities to the relevant stakeholders, such as the functional manager and the CEO, to avoid any confusion or conflict over the budget allocation1. References: 1: PMI Risk Management Professional (PMI-RMP)® Handbook, page 6.

The risk manager should have ensured a more accurate project work plan and budget to prevent the functional manager from requesting to use the project's contingency budget. A well-planned budget would have avoided the shortage in the functional manager's department budget.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free RMP questions practiced · - overall accuracy

You've reached the last free page. Unlock the full bank to keep going.

Want the full RMP question bank?

Unlock all 245 questions with mock exam, explanations for every option and domain-level analytics.

Page 8 of 8 · Questions 71-80 of 80 free

PracticeTestMaster is an independent exam prep provider. RMP is the property of PMI.

Full access

Unlock all 245 RMP questions

You're practicing 80 free questions. Paid plans add:

  • 165 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your RMP progress

Questions answered0
Accuracy-

Saved on this device.

RMP exam overview

Exam
PMI Risk Management Professional (PMI-RMP)
Code
RMP
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 245 questionsFrom $19.99
Unlock