Question 11

During a project team meeting, a risk manager realizes that the initial assumptions on the project schedule are too optimistic. The risk manager believes that the project might not meet its deadline as initially stated.

What is the reason for misunderstanding the assumptions from the beginning?

Correct answer: C

Explanation

Relying solely on historical project results for new assumptions can cause errors, as unique circumstances may differ. The PMBOK® Guide notes:

"Assumptions should be validated as part of project planning. Overreliance on past project data without proper contextual analysis can result in unrealistic expectations."

— PMBOK® Guide, 6th Edition, Section 11.2

[References:, PMBOK® Guide, 6th Edition, Section 11.2, ]

Question 12

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

Correct answer: D

Explanation

 

When stakeholders are concerned about the potential impact of a project, such as staff reductions, the risk manager should perform a stakeholder analysis. This analysis will help identify the stakeholders’ interests, their levels of influence, and how their concerns should be addressed in the project plan. By understanding these factors, the project team can develop strategies to engage stakeholders effectively, address their concerns, and increase project support. PMI emphasizes the importance of stakeholder analysis in risk management as it helps in aligning stakeholder expectations with project goals​​.

 

Question 13

A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.

What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)

Select 2 answers.

Correct answer: A, E

Explanation

The risk manager should have their team review the scope of work and requirements to ensure they understand the project's objectives and deliverables. Additionally, reviewing the risk management plan will help the team understand the risk management process, roles, and responsibilities, and prepare for the risk identification workshop.

According to the PMBOK® Guide – Sixth Edition1, the scope of work and requirements are key inputs for the risk identification process, as they define the project boundaries, deliverables, assumptions, and constraints. The risk management plan is also an essential input, as it provides the guidelines and framework for how risk management will be performed throughout the project. The other options are not relevant for risk identification, as they are either related to other processes (such as Monte Carlo analysis for quantitative risk analysis) or not directly related to the project risks (such as the list of pre-approved contractors or the organization chart for city permit department). References: PMBOK® Guide – Sixth Edition, pages 397-398.

Question 14

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

Correct answer: D

Explanation

 

In projects where team members are spread across multiple time zones and have not worked together before, fostering collaboration is critical. Developing a start-up workshop, where team members can meet (either virtually or physically if colocation is possible), helps in building relationships, aligning on project goals, and understanding roles. This approach can mitigate communication challenges and improve team cohesion, which are essential for effective risk management and overall project success. PMI emphasizes the importance of early team alignment and relationship-building in the risk management process​.

 

Question 15

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Correct answer: D

Explanation

 According to the PMBOK Guide, 6th edition, Section 11.6.2.1, Sensitivity Analysis, a sensitivity analysis is a technique that helps to determine which individual project risks or other sources of uncertainty have the most potential impact on project outcomes. A sensitivity analysis can be used to prioritize risks based on their relative effect on the project objectives, such as cost, schedule, quality, or scope. A sensitivity analysis can also help to identify areas where risk response efforts may be most effective. Therefore, the risk manager should perform a sensitivity analysis and determine the correct priority of every identified risk, rather than agreeing with the SME or the project sponsor, or marking every risk with the same or different priority without proper analysis. References: PMBOK Guide, 6th edition, Section 11.6.2.1, Sensitivity Analysis1

The risk manager should perform a sensitivity analysis to assess the impact of each risk on the project objectives. This will help in determining the correct priority of every identified risk, ensuring that resources are allocated effectively and that the most critical risks are addressed first.

Question 16

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Correct answer: C

Explanation

The full risk description is the first thing that the risk manager should complete before moving forward with the risk response planning. The full risk description is a detailed statement that describes the risk, its causes, its effects, and its context. It provides the basis for the risk analysis and the risk response planning. The risk categorization, the risk simul-ation, and the risk response plan are possible steps that the risk manager may take after completing the full risk description, but they are not the first thing to do. References: PMI Risk Management Professional (PMI-RMP)® Exam Content Outline1, PMI Practice Standard for Project Risk Management2, Risk Management Professional (PMI-RMP)® Cert Guide3

Question 17

A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.

What should the risk manager do in this case?

Correct answer: A

Explanation

 

If a risk requires external help and the contracting process is long, it is prudent to start the process immediately to avoid delays. This proactive approach ensures that the necessary resources will be available when needed. According to PMI guidelines, early action to address risk is essential, especially when external dependencies are involved. Documenting the risk in the risk register or analyzing it further can be done concurrently, but starting the contracting process mitigates the risk of delay​.

 

 

 

Question 18

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.

What should the team perform in this scenario?

Correct answer: A

Explanation

Quantitative risk analysis helps determine the minimum acceptable level of exposure and impact for each risk. It also helps to understand if the maximum level of exposure has been reached before escalating the risk. (Reference: PMBOK Guide, 6th Edition, p. 423)

The team should perform quantitative risk analysis, which is the process of numerically analyzing the effect of identified risks on overall project objectives. Quantitative risk analysis can help the team to establish the minimum acceptable level of exposure and impact for each risk, as well as the maximum level of exposure before escalation. Quantitative risk analysis can also provide probabilistic estimates of project outcomes, such as cost and schedule, and support risk prioritization and decision making. References: PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Sixth Edition, 2017, p. 399; PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 69.

Question 19

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Correct answer: C

Explanation

The project risk manager should generate reports to assess and communicate the project risk level to stakeholders. This helps in making informed decisions and taking appropriate actions to manage risks effectively.

 The project risk manager should quantify the risk exposure that exceeds project contingency, as this will help to determine the amount of management reserve needed to cover the potential cost overruns or schedule delays. The project risk manager should also communicate this information to the project manager and other relevant stakeholders, and update the risk management plan accordingly. References: The Standard for Risk Management in Portfolios, Programs, and Projects, page 80; PMBOK Guide, 6th edition, page 407.

Question 20

During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.

How should the risk manager address this concern?

Correct answer: C
0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free RMP questions practiced · - overall accuracy

Want the full RMP question bank?

Unlock all 245 questions with mock exam, explanations for every option and domain-level analytics.

Page 2 of 8 · Questions 11-20 of 80 free

PracticeTestMaster is an independent exam prep provider. RMP is the property of PMI.

Full access

Unlock all 245 RMP questions

You're practicing 80 free questions. Paid plans add:

  • 165 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your RMP progress

Questions answered0
Accuracy-

Saved on this device.

RMP exam overview

Exam
PMI Risk Management Professional (PMI-RMP)
Code
RMP
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 245 questionsFrom $19.99
Unlock