Question 31

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Correct answer: B

Explanation

 

 

With 25 identified risks, and considering the constraints and resources available, the appropriate next step is to perform a qualitative risk analysis. This process helps prioritize the risks based on their probability and impact, as well as other relevant factors like urgency, proximity, and detectability. By doing so, the team can focus on the most significant risks that require immediate attention and develop response plans accordingly, optimizing the use of available resources. PMI recommends this approach to ensure that risk management efforts are both efficient and effective in addressing the most critical risks first​.

 

Question 32

A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.

What should the risk manager do?

Correct answer: B

Explanation

Once a risk has been successfully managed, residual risks addressed, and there are no secondary risks, the next step according to risk management best practices is to formally close the expired risk and update all relevant project documentation. The PMBOK® Guide states:

"Once the risk responses have been implemented, and the risk is no longer a threat or opportunity, the risk should be closed out in the risk register and the results should be documented as part of project records and lessons learned."

— PMBOK® Guide, 6th Edition, Section 11.7.3.2

Closing the risk ensures transparency and supports organizational learning through updated project records.

[References:, PMBOK® Guide, 6th Edition, Section 11.7.3.2, Practice Standard for Project Risk Management, PMI, Section 6.7, ]

Question 33

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

Correct answer: B

Explanation

The risk manager should first update the risk register with the new risk identified by the vendor. This will help in keeping track of all the risks associated with the project and facilitate the subsequent planning and management of the risks.

 The risk manager should update the new risk in the risk register, which is a project document that records the details of all identified risks, including their description, category, cause, probability, impact, and response strategy. Updating the risk register is the first step to acknowledge the existence of the new risk and to document its characteristics and potential effects on the project objectives. The risk register can then be used as an input for the Plan Risk Responses process, where the risk manager can develop appropriate actions to address the new risk. References: PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Sixth Edition, 2017, p. 397, 441.

Question 34

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

Correct answer: A

Explanation

When a project experiences consistent deviations in cost performance index (CPI) and schedule performance index (SPI), it indicates underlying issues with the project's assumptions regarding schedule and resources. Analyzing these assumptions helps identify discrepancies between planned and actual performance, such as underestimated task durations or insufficient resource allocation. By revisiting and adjusting these assumptions, the risk manager can develop strategies to mitigate further overruns and align the project with its objectives.

PMI Risk Management Study Guide References:

The PMI-RMP Exam Content Outline emphasizes the importance of examining assumption and constraint analyses to identify risks arising from inaccurate or incomplete project assumptions, which can lead to performance issues.

Question 35

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Correct answer: B

Explanation

In risk management, to calculate the contingency budget for risks, we use the Expected Monetary Value (EMV) formula: EMV=Probability of Risk×Impact of Risk\text{EMV} = \text{Probability of Risk} \times \text{Impact of Risk}EMV=Probability of Risk×Impact of Risk

For Risk A:

Probability: 40% or 0.40

Impact: US$100,000\text{EMV of Risk A} = 0.40 \times 100,000 = US$40,000

For Risk B:

Probability: 60% or 0.60

Impact: US$20,000\text{EMV of Risk B} = 0.60 \times 20,000 = US$12,000

Total contingency budget = EMV of Risk A + EMV of Risk B

40,000 + 12,000 = US$52,000

Thus, the total contingency budget required for both risks is US$52,000. This approach follows PMI’s risk management guidelines, specifically under the "Quantitative Risk Analysis" process. This process focuses on determining numerical probabilities and monetary impacts to compute the expected financial impact of identified risks​​.

Question 36

A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.

What should the project manager do to avoid this risk?

Correct answer: D

Explanation

The project manager should address the communication risk by meeting the client's preference for face-to-face conversations. This can be achieved by planning face-to-face meetings for critical milestones.

 Communication issues with the client are a potential risk that can affect the project scope, schedule, quality, and stakeholder satisfaction. To avoid this risk, the project manager should align the communication methods and preferences with the client’s expectations and needs. If the client prefers face-to-face conversations, the project manager should respect that and meet the client in person whenever possible. This can help build trust, rapport, and clarity between the project manager and the client. The project manager should also plan for critical milestone meetings with the client to review the project progress, deliverables, and feedback. This can help ensure that the project is on track and meets the client’s requirements and satisfaction. References: PMI, 2017. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. Newtown Square, PA: Project Management Institute, Inc., pp. 376-3771

Question 37

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.

What type of request is the risk manager describing?

Correct answer: A

Explanation

 

The risk manager's request to include Field 2 in the scope of the current project is a clear attempt to increase the project’s profitability by expanding its scope to a more lucrative area. This type of request is aimed at increasing project earnings, as it involves altering the project’s objectives to capture a more significant financial opportunity.

According to PMI, requests that seek to modify project scope for financial gain are typically categorized as efforts to increase project earnings or revenue​​.

 

 

 

Question 38

A product roadmap should contain which of these primary components?

Correct answer: D

Explanation

Comprehensive and Detailed In-Depth Explanation:

A product roadmap is a strategic document that outlines the vision, direction, and progress of a product over time. It serves as a communication tool, aligning stakeholders on the product's goals and the plan to achieve them.

Option D: Product vision, business objectives, timeframes.

This option encapsulates the essential elements of a product roadmap:

Product Vision: Defines the long-term mission and purpose of the product, providing a clear direction and inspiration.

Business Objectives: Specific, measurable goals that the product aims to achieve, aligning with the organization's strategic aims.

Timeframes: Indicative timelines for achieving milestones, helping to set expectations and facilitate planning.

The PMI-RMP® Exam Prep Study Guide highlights that "a well-structured product roadmap includes the product vision, aligned business objectives, and projected timeframes to guide development and stakeholder communication" (Fremouw, 2021, p. 89).

Option A: Detailed design plan, business objectives, timeframes.

While business objectives and timeframes are integral to a product roadmap, a detailed design plan is typically too granular for this high-level document. The roadmap focuses on overarching goals and timelines rather than specific design details.

Option B: Project management plan, communications management plan, stakeholder engagement plan.

These components are elements of project management planning but do not constitute a product roadmap. They pertain to the processes and methodologies of managing a project rather than outlining the strategic direction of a product.

Option C: Project release timeframes, detailed design plan.

Project release timeframes are relevant to a product roadmap; however, combining them solely with a detailed design plan omits the critical aspects of product vision and business objectives, which are necessary to provide context and purpose.

In summary, a comprehensive product roadmap should primarily include the product vision, business objectives, and timeframes (Option D), offering a strategic overview that guides the product's development and aligns stakeholders with its intended direction.

[References:, Fremouw, B. (2021). PMI-RMP® Exam Prep Study Guide. RMC Publications., , , , ]

Question 39

During project execution for a software development program, a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

Correct answer: D

Explanation

Assumptions made during planning need to be reviewed to understand deviations in actual results. PMBOK® Guide states:

"Reviewing project assumptions is key to understanding variances between planned and actual performance, as invalid or changed assumptions often cause project deviations."

— PMBOK® Guide, 6th Edition, Section 11.2

[References:, PMBOK® Guide, 6th Edition, Section 11.2, ]

Question 40

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?

Correct answer: A

Explanation

The project risk manager should monitor risk thresholds closely, as they represent the organization's risk appetite. In a project with a low risk appetite, it is essential to ensure that risks are managed within the defined thresholds to address stakeholders' concerns and maintain their confidence in the project's success.

According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, risk thresholds are the measure of acceptable variation around an objective that reflects the risk appetite of the organization1. Risk appetite is the degree of uncertainty an entity is willing to take on in anticipation of a reward2. In this case, the project has a significant impact on the organization and the stakeholders have a low risk appetite, meaning they are not willing to accept much deviation from the project objectives. Therefore, the project risk manager should monitor the risk thresholds closely to ensure that the project risks do not exceed the acceptable level of variation and impact the project performance negatively. By monitoring the risk thresholds, the project risk manager can also identify when risk responses are needed and evaluate their effectiveness.

[References: 1: PMI, Practice Standard for Project Risk Management, 2009, p. 20 2: PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Sixth Edition, 2017, p. 720, , , ]
0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free RMP questions practiced · - overall accuracy

Want the full RMP question bank?

Unlock all 245 questions with mock exam, explanations for every option and domain-level analytics.

Page 4 of 8 · Questions 31-40 of 80 free

PracticeTestMaster is an independent exam prep provider. RMP is the property of PMI.

Full access

Unlock all 245 RMP questions

You're practicing 80 free questions. Paid plans add:

  • 165 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your RMP progress

Questions answered0
Accuracy-

Saved on this device.

RMP exam overview

Exam
PMI Risk Management Professional (PMI-RMP)
Code
RMP
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 245 questionsFrom $19.99
Unlock