Question 41

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Correct answer: D

Explanation

If the project manager realizes that some risks have not been updated recently, they should review the risk register to check for new risks and ensure that all risks are accurately documented and updated.

The risk register is a document that contains information about the identified risks, their analysis, and their response plans. It is updated throughout the project life cycle as new risks emerge, existing risks change, or risks are closed. The project manager should review the risk register regularly to ensure that the project data is accurate and reflects the current risk situation. Reviewing the risk register also helps the project manager to identify any new risks that may have occurred since the last update, and to plan appropriate responses for them. References: PMI, Project Risk Management, 2nd edition, 2019, p. 67-681

Question 42

The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.

What should the risk management team have done to manage this situation?

Correct answer: C

Explanation

Effective communication with sponsors and stakeholders about both primary and secondary risks is crucial. PMBOK® Guide states:

"Secondary risks... should be communicated to stakeholders and sponsors to ensure transparency and allow for appropriate responses."

— PMBOK® Guide, 6th Edition, Section 11.5

[References:, PMBOK® Guide, 6th Edition, Section 11.5, ]

Question 43

A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.

What is the expected outcome of developing the risk management plan?

Correct answer: B

Explanation

The expected outcome of developing the risk management plan is to define how risk management activities will be executed throughout the project. This includes the processes, tools, and techniques that will be used to identify, assess, and manage risks.

 The risk management plan is a document that describes how risk management activities will be structured and performed throughout the project. It provides guidance on how to identify, analyze, respond, monitor, and control risks, as well as how to communicate, document, and report them. The risk management plan also defines the roles and responsibilities of the project team and stakeholders in risk management, the risk categories and breakdown structure, the risk thresholds and appetite, the risk management tools and techniques, and the risk management budget and schedule. The risk management plan is an output of the plan risk management process, which is the first process in the project risk management knowledge area. Developing the risk management plan is essential for ensuring that the project risks are closely managed and aligned with the project objectives and stakeholder expectations. References: PMI, Project Risk Management, 2nd edition, 2019, p. 67-681

Question 44

The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

Select 2 answers.

Correct answer: A, C

Explanation

The risk manager should consult the risks that have materialized and the overall risk profile to analyze the performance of managing the risks, as well as the risks due to the number of claims submitted to the client. These options provide insights into how well risks are being managed and the potential impact on the project.

 The risk manager should consult the risks that have materialized and the overall risk profile, as these are indicators of how well the risk management process is working and how the project is affected by the risks. The risk manager should also consult the risks due to the number of claims submitted to the client, as these are potential sources of conflict, litigation, and reputation damage that may impact the project objectives and stakeholder satisfaction. References: The Standard for Risk Management in Portfolios, Programs, and Projects, page 83; PMBOK Guide, 6th edition, page 414.

Question 45

A company has been awarded a large government contract to develop a new transportation system. There is uncertainty surrounding the project's timeline. The project team is struggling to finalize the project's budget due to unclear estimates from vendors. An updated vendor price list detailing the costs of available technologies is an essential component in determining the project's final cost. The project team will not be able to finalize the project's timeline until the budget is finalized.

What should the risk manager do?

Correct answer: C

Explanation

The best practice is to log the risk and the associated response strategies in the risk register to ensure it is monitored, analyzed, and managed throughout the project. The PMBOK® Guide states:

"All identified risks and their planned responses should be recorded in the risk register to facilitate ongoing monitoring and management."

— PMBOK® Guide, 6th Edition, Section 11.2.3.1

Ignoring or treating these as mere assumptions could result in unmanaged risks and potential project failure.

[References:, PMBOK® Guide, 6th Edition, Section 11.2.3.1, Practice Standard for Project Risk Management, PMI, Section 5.3, , , ]

Question 46

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Select 3 answers.

Correct answer: A, B, D

Explanation

During risk identification, the risk manager should ensure the following actions are performed:

A. Develop checklists based on historical information: Checklists are valuable tools in risk identification as they draw from previous projects' experiences and ensure that commonly encountered risks are not overlooked.

B. Conduct interviews, meetings, and focus groups: These are key methods for gathering qualitative data from stakeholders, which can reveal potential risks based on their experiences and expectations.

D. Employ brainstorming to generate spontaneous ideas: Brainstorming is an effective technique for generating a wide range of potential risks quickly, allowing the project team to explore various scenarios and possibilities.

These actions align with PMI’s best practices for comprehensive risk identification, ensuring that all possible risks are considered and documented​​.

 

 

Question 47

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

Correct answer: D

Explanation

The project manager should apply an iterative approach to risk identification, which involves continuous risk identification throughout the project lifecycle. This will help to identify and address new risks that may arise during the project.

According to the PMBOK® Guide, risk identification is the process of determining which risks may affect the project and documenting their characteristics. It is an iterative process because new risks may evolve or become known only as the project progresses through its life cycle. There are many techniques available for risk identification and assessment, such as brainstorming, interviews, checklists, SWOT analysis, cause and effect diagrams, etc. The project manager should apply an iterative approach to risk identification to ensure that all relevant risks are captured and updated throughout the project. The project manager should also involve the project team and other stakeholders in the risk identification process to obtain their input and perspectives.

The other options are not valid for the next step after explaining the importance of risk management to the team:

Review assumptions and constraints around risks: This is a technique for risk identification, but it is not the only one. The project manager should use a combination of techniques to identify risks, not just focus on one aspect. Also, reviewing assumptions and constraints is not the same as applying an iterative approach, which implies repeating the risk identification process at regular intervals or when changes occur.

Develop the risk response plans for identified risks: This is a step in the Plan Risk Responses process, which comes after the Perform Qualitative Risk Analysis and Perform Quantitative Risk Analysis processes. The project manager should not develop the risk response plans before identifying and analyzing the risks.

Determine the likelihood and impact of the risks: This is a step in the Perform Qualitative Risk Analysis process, which comes after the Identify Risks process. The project manager should not determine the likelihood and impact of the risks before identifying them.

PMBOK® Guide1, Risk Management Professional (PMI-RMP)® Cert Guide

Question 48

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource's availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.

What should the risk manager do next?

Correct answer: B

Explanation

 

Once the contingency plan has been executed (e.g., the backup resource has shadowed the experienced developer), it is crucial to continuously monitor and manage any residual or secondary risks that may arise. These risks could include the backup resource's ability to perform effectively or the potential impact of the original developer's absence on project timelines. By updating the risk register and maintaining communication with the project team, the risk manager ensures that the project remains on track and that any new risks are promptly addressed, in alignment with PMI’s best practices for ongoing risk management​.

 

Question 49

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Correct answer: C

Explanation

In risk management, it is common that not all risks can be completely eliminated. Residual risk is the remaining risk after all possible mitigation efforts have been applied. If the residual risk is within the organization’s risk appetite—meaning the organization is willing to accept this level of risk—it is appropriate to proceed with the plan. The PMI framework supports this approach, as risk management is about balancing effort and benefit, ensuring that mitigation efforts are commensurate with the risk involved​.

 

 

Question 50

A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.

What should the risk manager advise the project team?

Correct answer: D

Explanation

In situations where available time and funds are insufficient to address all identified risks, it's imperative to prioritize risks based on their potential impact on the project. Focusing on high-impact risks ensures that the most critical threats to project success are managed effectively within the constraints. This approach involves conducting a thorough risk assessment to categorize risks by their severity and likelihood, allowing the project team to allocate resources strategically. By concentrating on high-impact risks, the team can develop contingency plans that safeguard the project's primary objectives, even if lower-impact risks cannot be fully mitigated due to resource limitations.

PMI Risk Management Study Guide References:

The PMI-RMP Exam Preparation Study Guide emphasizes the importance of prioritizing risks, stating that "project teams often face constraints in resources, making it essential to focus on risks that pose the greatest threat to project objectives."

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free RMP questions practiced · - overall accuracy

Want the full RMP question bank?

Unlock all 245 questions with mock exam, explanations for every option and domain-level analytics.

Page 5 of 8 · Questions 41-50 of 80 free

PracticeTestMaster is an independent exam prep provider. RMP is the property of PMI.

Full access

Unlock all 245 RMP questions

You're practicing 80 free questions. Paid plans add:

  • 165 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your RMP progress

Questions answered0
Accuracy-

Saved on this device.

RMP exam overview

Exam
PMI Risk Management Professional (PMI-RMP)
Code
RMP
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 245 questionsFrom $19.99
Unlock