Question # 46

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.

Develop checklists based on historical information

B.

Conduct interviews, meetings, and focus groups

C.

Assign a different risk manager for each portfolio unit

D.

Employ brainstorming to generate spontaneous ideas

E.

Perform qualitative and quantitative risk analyses 

Question # 47

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

Options:

A.

Review assumptions and constraints around risks.

B.

Develop the risk response plans for identified risks.

C.

Determine the likelihood and impact of the risks.

D.

Apply an iterative approach to risk identification.

Question # 48

An experienced and the only developer on a software implementation project will be on leave for several weeks. The risk of this critical resource's availability was added to the risk register. Contingencies were made for a support developer to job shadow this resource, depending on how things go prior to their leave. The project team was pleased with the backup plan and the new resource was able to shadow for a few weeks.

What should the risk manager do next?

Options:

A.

Update the risk register to indicate the risk has occurred and close out the expired risk from the register.

B.

Update, continuously monitor, and communicate the residual and secondary risks of the backup resource on the project.

C.

Hire a permanent developer to support the project, and work with the backup resource to eliminate this risk.

D.

Hire another developer to support the project, contingent on when the experienced developer returns. 

Question # 49

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Options:

A.

Accept the response because there are no secondary risks were identified.

B.

The response plan should be discontinued and the risk should be accepted and dealt with if it occurs.

C.

Accept the residual risk as it is compatible with the organization's risk appetite.

D.

All identified risks must be addressed because they might significantly impact the project if they occur. 

Question # 50

A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.

What should the risk manager advise the project team?

Options:

A.

Ask the project sponsor for more time and funds if needed.

B.

Create a change request if there are additional needs based on the risk responses.

C.

Accept some risks might not be materialized so no extra time and funds will be needed.

D.

Focus on the high-impact risk for contingency planning purposes.

Viewing page 10 out of 15 pages

Try free RMP sample questions and upgrade to complete 245 questions bank & timed simulator.

RMP Practice Test Main Page

Don't just take our word for it. Industry research shows that targeted RMP certification practice questions MCQs dramatically increases pass rates for the PMI Risk Management Professional (PMI-RMP). Our platform is built on this principle, offering the most realistic simulations available to give you that proven advantage.


RMP Overview

Name PMI Risk Management Professional (PMI-RMP)
Code RMP
Vendor Professional
Certification PMI

Our free RMP exam questions sample is your personalized diagnostic tool. Get an instant, honest snapshot of your readiness for the PMI Risk Management Professional (PMI-RMP) exam and identify the specific topics that need your focus.

RMP Questions

What You Get with Full Access:

Complete Question Bank

Timed Exam Simulator

Smart Performance Dashboard

Identify Weak Spots

Verified Answer & Explanations

Unlimited Reattempts

Mobile-Friendly Study

Regular Content Updates



1 Month Access

$19.99

Buy Now


12 Months Access

$49.99

Buy Now

RMP Complete Package

Choose a plan and prepare with realistic RMP test questions designed to mirror test-day conditions. Every plan includes a full PMI Risk Management Professional (PMI-RMP) practice exam questions, a timed exam simulator, performance tracking, detailed answer explanations, and the ability to reattempt questions to improve accuracy and confidence.

245 Practice Questions - Flexible Quiz Modes - Unlimited Attempts