Question # 41

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.

Review the assumptions analysts

B.

Conduct a checklist analysis on each risk

C.

Create a risk response plan for those risks

D.

Review the risk register to check for the new risks

Question # 42

The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.

What should the risk management team have done to manage this situation?

Options:

A.

Ensured to include the stakeholders in the team discussions

B.

Encouraged involvement of the project team during the review meetings

C.

Enhanced communication with the sponsor regarding secondary risk impact

D.

Ensured the sponsor got more involved with the project risk planning

Question # 43

A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.

What is the expected outcome of developing the risk management plan?

Options:

A.

Being able to monitor and control risks throughout the project.

B.

Defining how risk management will be executed throughout the project.

C.

Documenting the communication strategy for risks throughout the project.

D.

Having the ability to identify risks throughout the project.

Question # 44

The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

Options:

A.

Proximity dales for open risks

B.

Backlog of change orders to be submitted to client

C.

Risks that have materialized and the overall risk profile

D.

Number of schedule baseline changes approved

E.

Risks due to the number of claims submitted to the client

Question # 45

A company has been awarded a large government contract to develop a new transportation system. There is uncertainty surrounding the project's timeline. The project team is struggling to finalize the project's budget due to unclear estimates from vendors. An updated vendor price list detailing the costs of available technologies is an essential component in determining the project's final cost. The project team will not be able to finalize the project's timeline until the budget is finalized.

What should the risk manager do?

Options:

A.

Request an extension to mitigate schedule constraints.

B.

Register the risks as vendor issues and avoid further action.

C.

Log the risk and the response strategies in the risk register.

D.

Catalog the risks as assumptions and avoid further action.

Viewing page 9 out of 15 pages

Try free RMP sample questions and upgrade to complete 245 questions bank & timed simulator.

RMP Practice Test Main Page

Don't just take our word for it. Industry research shows that targeted RMP certification practice questions MCQs dramatically increases pass rates for the PMI Risk Management Professional (PMI-RMP). Our platform is built on this principle, offering the most realistic simulations available to give you that proven advantage.


RMP Overview

Name PMI Risk Management Professional (PMI-RMP)
Code RMP
Vendor Professional
Certification PMI

Our free RMP exam questions sample is your personalized diagnostic tool. Get an instant, honest snapshot of your readiness for the PMI Risk Management Professional (PMI-RMP) exam and identify the specific topics that need your focus.

RMP Questions

What You Get with Full Access:

Complete Question Bank

Timed Exam Simulator

Smart Performance Dashboard

Identify Weak Spots

Verified Answer & Explanations

Unlimited Reattempts

Mobile-Friendly Study

Regular Content Updates



1 Month Access

$19.99

Buy Now


12 Months Access

$49.99

Buy Now

RMP Complete Package

Choose a plan and prepare with realistic RMP test questions designed to mirror test-day conditions. Every plan includes a full PMI Risk Management Professional (PMI-RMP) practice exam questions, a timed exam simulator, performance tracking, detailed answer explanations, and the ability to reattempt questions to improve accuracy and confidence.

245 Practice Questions - Flexible Quiz Modes - Unlimited Attempts