Question 61

A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the

client's vendor, which apparently has been causing all of the issues.

What should the risk manager do first?

Correct answer: D

Explanation

The risk registry is a document that records the identified risks, their characteristics, their status, and their responses. It is a key input for risk management and a source of information for project stakeholders. The risk manager should review the risk registry first to understand the current state of the project risks, especially the ones related to the client’s vendor, and to evaluate the effectiveness of the risk responses implemented so far. Enhancing risk identification, reviewing the contingency reserves, and creating a risk response plan are possible actions that the risk manager may take after reviewing the risk registry, but they are not the first thing to do. References: PMI Risk Management Professional (PMI-RMP)® Exam Content Outline1, PMI Practice Standard for Project Risk Management2, Risk Management Professional (PMI-RMP)® Cert Guide3

Question 62

A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

Correct answer: A

Explanation

An Ishikawa diagram (also known as a fishbone or cause-and-effect diagram) is a tool used to identify and analyze the root causes and sources of a risk. It helps the risk manager gain a deeper understanding of the risk source and likelihood. (Reference: PMBOK Guide, 6th Edition, p. 139)

 An Ishikawa diagram, also known as a fishbone diagram or a cause-and-effect diagram, is a tool that can help the risk manager to analyze the root causes of a risk and to identify the factors that influence its occurrence and impact. An Ishikawa diagram can also help to visualize the relationships among different causes and to prioritize the most significant ones. By developing and employing an Ishikawa diagram, the risk manager can gain a deeper understanding of the source and likelihood of the risk and plan appropriate responses accordingly. References: The Standard for Risk Management in Portfolios, Programs, and Projects, page 72; PMBOK Guide, 6th edition, page 398.

Question 63

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

Correct answer: B

Explanation

The risk manager can ensure the organizational process assets (OPAs) are updated as a result of risk management activities by arranging periodic risk management process audits. These audits help evaluate the effectiveness of risk management processes and identify areas of improvement, leading to updates in the OPAs.

According to the PMBOK Guide, one of the tools and techniques for the monitor risks process is audits. Audits are examinations of the risk management processes to ensure that they are aligned with the project objectives and are following the organizational policies and procedures. Audits can also identify any gaps, inconsistencies, or areas of improvement in the risk management activities. By conducting periodic audits, the risk manager can ensure that the organizational process assets are updated and reflect the current state of the project risk management. Some of the organizational process assets that can be updated as a result of audits are risk management templates, risk categories, risk databases, and lessons learned1 . References: PMBOK Guide, 6th edition, pages 456-457, 481-4821; PMI-RMP Exam Content Outline, 2015, page 9

Question 64

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Correct answer: A

Explanation

The project manager should monitor and control secondary and residual risks in the risk register. This will ensure that any new risks identified during the implementation of the risk response plan are captured and managed effectively. Monitoring and controlling risks is a continuous process that helps in identifying, analyzing, and planning for new risks as well as updating the risk register as needed.

 According to the PMI Risk Management Professional (PMI-RMP)® Examination Content Outline, one of the tasks under the domain of Risk Response Planning is to “identify and assess the effectiveness of alternative strategies to reduce threats or enhance opportunities, such as mitigation, transference, avoidance, and acceptance” 1. This implies that the project manager should also consider the potential secondary or residual risks that may arise from implementing the chosen risk response strategy. Secondary risks are new risks that are created as a direct result of implementing a risk response, while residual risks are those that remain after the risk response has been executed 2. Both types of risks should be identified and assessed for their impact and probability, and added to the risk register for further monitoring and control. Therefore, the correct answer is A.

[References: 1: PMI Risk Management Professional (PMI-RMP)® Examination Content Outline, page 91 2: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, page 4362, , ]

Question 65

Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?

Correct answer: B

Explanation

The risk manager should increase stakeholder risk appetite by explaining risk handling and mitigation strategies, which will help stakeholders understand how risks can be managed and reduced, making them more comfortable with the risk process.

The best way to increase stakeholder risk appetite is to explain risk handling and mitigation strategies, which are the actions taken to reduce the probability and/or impact of risks, or to enhance the opportunities. By doing so, the risk manager can help the stakeholders understand how the risks can be managed effectively and efficiently, and how the potential benefits can outweigh the potential costs. This can also increase the stakeholder confidence and trust in the risk process and the project outcomes. The other options are not appropriate ways to increase stakeholder risk appetite. Excluding risk averse stakeholders from future risk discussions can alienate them and create conflicts. Increasing the impact of all risks in the risk breakdown structure (RBS) can exaggerate the risk exposure and create unnecessary fear and anxiety. Developing a generous probabilistic cash flow model can create unrealistic expectations and lead to poor decision making. References: PMI Risk Management Professional (PMI-RMP) Examination Content Outline and Specifications, page 81. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, pages 403-4042.

Question 66

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?

Correct answer: B

Explanation

 According to the PMBOK Guide, one of the tools and techniques for the plan risk management process is ground rules. Ground rules are the rules of conduct or behavior that are established by the project team and other stakeholders to ensure a productive and respectful environment for risk management activities. Ground rules can cover various aspects of risk management, such as roles and responsibilities, communication protocols, decision-making processes, meeting agendas, and conflict resolution methods1. By referring to the team’s ground rules on how to resolve conflicts, the risk manager can handle the situation where two key external stakeholders are overemphasizing the impact of a few project risks. This can help the risk manager to maintain a constructive and collaborative atmosphere in the risk reassessment workshop, as well as to ensure that the risk analysis and prioritization are based on objective and consistent criteria.

Some of the other options are not relevant or appropriate for the question scenario:

Requesting for a skilled facilitator to help resolve conflicts that have arisen is not a feasible or effective option, as it would interrupt the flow of the risk reassessment workshop and delay the risk management process. The risk manager should be able to facilitate the workshop and handle conflicts by themselves, using the tools and techniques that they have planned and agreed upon with the project team and stakeholders.

Running a sensitivity analysis to check which risks have the most impact is a technique for the perform quantitative risk analysis process, which is not applicable in the context of a risk reassessment workshop. A sensitivity analysis is a quantitative method that examines the effect of varying one risk parameter at a time on the project objectives, such as cost or schedule. It is not a tool for resolving conflicts or validating the impact of risks, as it does not consider the interrelationships and dependencies among risks or the probability of risk occurrence1.

Using the assumption analysis technique to validate the assumptions is a technique for the identify risks process, which is not suitable for the situation where conflicts have already arisen in the risk reassessment workshop. An assumption analysis is a technique that explores the validity of the assumptions that are made during the project planning and risk management processes. It is not a tool for resolving conflicts or verifying the impact of risks, as it does not address the root causes or the consequences of the disagreements among the stakeholders1.

PMBOK Guide, 6th edition, pages 407-408, 431-432, 437-438, 441-4421; PMI-RMP Exam Content Outline, 2015, pages 7-8.

Question 67

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Correct answer: A

Explanation

According to the PMBOK® Guide, a scope change request is a formal proposal to modify any project document, deliverable, or baseline. It is an output of the Perform Integrated Change Control process, which is the process of reviewing all change requests, approving changes, and managing changes to the deliverables, organizational process assets, project documents, and the project management plan. A scope change request may introduce new risks or affect existing risks on the project, which may impact the project objectives, such as scope, schedule, cost, and quality.

The risk manager should support the project manager with the scope change request by evaluating any new risks that are introduced due to the change in scope. This is because the risk manager is responsible for planning, implementing, and monitoring the risk management activities on the project, as well as communicating and reporting the risk information to the project manager and other stakeholders. The risk manager should use the appropriate risk identification and analysis techniques, such as brainstorming, interviews, checklists, SWOT analysis, cause and effect diagrams, probability and impact assessment, etc., to identify and evaluate the new risks that may arise from the scope change. The risk manager should also document the new risks in the risk register, which is a project document that contains the details of all identified individual project risks and other relevant information.

The other options are not valid for what the risk manager should do to support the project manager with the scope change request:

Update the risk management plan to reflect the scope change: This is not a valid option because the risk management plan is a component of the project management plan, which describes how risk management activities will be structured and performed on the project. It is an output of the Plan Risk Management process, which is the process of defining how to conduct risk management activities for a project. The risk management plan should not be updated to reflect the scope change, but rather to reflect any changes in the risk management approach, methodology, roles and responsibilities, budget, timing, risk categories, definitions, reporting formats, etc. The risk management plan should be updated only when there is a change in the risk management process, not in the project scope.

Reassess the identified risks that impact the project scope: This is not a valid option because reassessing the identified risks that impact the project scope is part of the Monitor Risks process, which is the process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project. The risk manager should not reassess the identified risks that impact the project scope before evaluating any new risks that are introduced due to the change in scope. The risk manager should first identify and analyze the new risks, and then reassess the existing risks to determine if they are still valid, relevant, and prioritized.

Update the risk register to identify, analyze, and plan a response for any new risk: This is not a valid option because updating the risk register to identify, analyze, and plan a response for any new risk is a combination of several risk management processes, such as Identify Risks, Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, and Plan Risk Responses. The risk manager should not update the risk register to identify, analyze, and plan a response for any new risk in one step, but rather follow the sequential and iterative risk management processes to ensure a comprehensive and consistent risk management approach. The risk manager should also coordinate and communicate with the project manager and other stakeholders when updating the risk register, as well as obtain their approval and input.

PMBOK® Guide1, Risk Management Professional (PMI-RMP)® Cert Guide1

Question 68

A stakeholder is asking a project team to hire an external vendor with more expertise and capacity to accelerate a delivery plan. The team has some concerns about this request. What should the risk manager do first?

Correct answer: C

Explanation

Before deciding to hire an external vendor to accelerate the delivery plan, it's essential to assess the potential internal and external factors that could influence this decision. Conducting a SWOT analysis allows the project team to systematically evaluate:

Strengths: Internal capabilities that could support the decision.

Weaknesses: Internal limitations or challenges.

Opportunities: External factors the project could capitalize on.

Threats: External factors that could pose risks.

This comprehensive assessment provides a balanced perspective, enabling informed decision-making regarding the engagement of an external vendor.

PMI Risk Management Study Guide References:

The PMI-RMP Exam Content Outline lists SWOT analysis as a technique for assessing project risk complexity and identifying potential threats and opportunities, facilitating informed decision-making in project risk management.

Question 69

A newly appointed risk manager for a critical project is working with a project team to develop a risk management strategy. One team member suggested creating an influence diagram to help analyze the options, risks, outcomes, and their relationships. Another team member feels the influence diagram is not enough because this project is important and complex.

Which approach should the risk manager take to improve the quality of the project risk analysis?

Correct answer: D

Explanation

The correct answer is D. Use a qualitative or quantitative analysis to analyze identified risks.

An influence diagram is useful for showing relationships among decisions, uncertainties, and outcomes, but it is not usually sufficient by itself for a complete risk analysis on a critical and complex project. Once risks are identified and their relationships are understood, the risk manager should perform qualitative and, where needed, quantitative analysis to assess probability, impact, priority, and potential effect on project objectives.

This makes option D the best answer because it directly strengthens the depth and rigor of the project’s risk analysis. Qualitative analysis helps prioritize risks based on relative importance, while quantitative analysis can estimate numeric effects on cost, schedule, or performance for the most significant risks.

Why the other options are incorrect:

    A. Use brainstorming to identify more possible risks.Brainstorming is mainly a risk identification technique, not the best answer for improving the quality of analysis after risks and relationships are already being examined.

    B. Use a Monte Carlo simulation to identify risks.Monte Carlo simulation is not used to identify risks. It is a quantitative analysis technique used after risks and uncertainty inputs have already been identified.

    C. Use a work breakdown structure (WBS) to help analyze risks.A WBS can help organize project work and may support identification by revealing areas of uncertainty, but it is not the strongest answer for enhancing the actual quality of risk analysis.

Best-practice reasoning:

For important and complex projects, risk analysis should move beyond simple diagramming techniques and include formal qualitative and quantitative methods. This creates a more reliable basis for prioritization, response planning, and decision-making.

Reference-aligned basis:

This answer is consistent with standard risk management guidance that emphasizes:

    qualitative and quantitative techniques for deeper risk assessment,

    the use of analytical methods after risk identification,

    improved decision quality through structured analysis of uncertainty.

[References:, PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Perform Qualitative Risk Analysis and Perform Quantitative Risk Analysis, PMI, Practice Standard for Project Risk Management, ISO 31000, risk analysis and evaluation principles, ============]

Question 70

A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.

How should a professional risk manager manage the risks in such situations?

Correct answer: B

Explanation

In a company with rapidly changing work conditions and difficulty in predicting long-term business plans, a professional risk manager should adopt agile approaches to manage the risks (B). Agile approaches allow for flexibility, adaptability, and quick response to changes, making them suitable for managing risks in such situations. This is supported by the PMI's PMBOK Guide, Sixth Edition, and the Agile Practice Guide.

 A professional risk manager should adopt agile approaches to manage the risks in situations where the company accommodates a lot of innovation and changing work conditions, and experiences difficulty in predicting long term business plans. Agile approaches are adaptive, iterative, and collaborative methods that focus on delivering value and reducing uncertainty in a dynamic and complex environment. Agile approaches can help the risk manager to identify, analyze, respond, and monitor risks in a flexible and timely manner, by using tools and techniques such as risk-adjusted backlog, risk burndown charts, risk-based spike, and risk-based testing. Agile approaches can also help the risk manager to engage the stakeholders and the project team in risk management activities, by using practices such as daily stand-up meetings, sprint planning, sprint review, and sprint retrospective. Agile approaches can enable the risk manager to manage the risks effectively and efficiently, by aligning the risk management strategy with the project goals and the customer needs. Adopting a predictive approach to manage the risks is not the best option, as it may not be suitable or feasible for situations where the project scope, schedule, and budget are uncertain or variable. A predictive approach is a plan-driven and sequential method that relies on upfront planning and detailed documentation to manage the risks. A predictive approach may not be able to cope with the frequent changes and emerging risks that may occur in an innovative and dynamic environment. Utilizing proper documentation to help manage the risks is not the best option, as it may not be sufficient or effective for situations where the project requirements and deliverables are evolving or changing. Proper documentation is a useful and necessary component of risk management, but it is not a substitute for agile risk management practices. Proper documentation may not be able to capture and communicate the current and relevant information about the risks and their impacts in a timely and accurate manner. Conducting weekly risk management meetings with all stakeholders is not the best option, as it may not be optimal or efficient for situations where the project risks and opportunities are changing rapidly or frequently. Weekly risk management meetings are a common and beneficial practice for risk management, but they may not be enough or appropriate for agile risk management. Weekly risk management meetings may not be able to address the risks and their responses as soon as they arise or occur, and they may not be able to involve all the relevant and available stakeholders and project team members. References: 3, 4, 5

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free RMP questions practiced · - overall accuracy

Want the full RMP question bank?

Unlock all 245 questions with mock exam, explanations for every option and domain-level analytics.

Page 7 of 8 · Questions 61-70 of 80 free

PracticeTestMaster is an independent exam prep provider. RMP is the property of PMI.

Full access

Unlock all 245 RMP questions

You're practicing 80 free questions. Paid plans add:

  • 165 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your RMP progress

Questions answered0
Accuracy-

Saved on this device.

RMP exam overview

Exam
PMI Risk Management Professional (PMI-RMP)
Code
RMP
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 245 questionsFrom $19.99
Unlock