Question # 31

A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.

What should the risk manager do?

Options:

A.

Perform a sensitivity analysis.

B.

Perform a qualitative risk analysis.

C.

Perform a constraint analysis.

D.

Perform a root-cause analysis. 

Question # 32

A project team successfully implemented a risk response plan for a major risk event. Residual risks were evaluated and actions were taken to keep them under control. There were no secondary risks after the implementation.

What should the risk manager do?

Options:

A.

Study the change logs to implement the approved change requests.

B.

Close out the expired risk and update the relevant project documents.

C.

Get permission from stakeholders before documenting lessons learned.

D.

Continue monitoring the critical response plan on the delivered product.

Question # 33

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

Options:

A.

Update the new risk in the risk register.

B.

Plan responses for the new risk.

C.

Passively accept the new risk.

D.

Add the new risk to the watch list.

Question # 34

A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.

Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?

Options:

A.

Schedule and resource assumptions

B.

Contingency reserves

C.

Work breakdown structure (WBS)

D.

Risk impact matrix

Question # 35

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Options:

A.

US$68,000

B.

US$52,000

C.

US$120,000

D.

US$80,000

Viewing page 7 out of 15 pages

Try free RMP sample questions and upgrade to complete 245 questions bank & timed simulator.

RMP Practice Test Main Page

Don't just take our word for it. Industry research shows that targeted RMP certification practice questions MCQs dramatically increases pass rates for the PMI Risk Management Professional (PMI-RMP). Our platform is built on this principle, offering the most realistic simulations available to give you that proven advantage.


RMP Overview

Name PMI Risk Management Professional (PMI-RMP)
Code RMP
Vendor Professional
Certification PMI

Our free RMP exam questions sample is your personalized diagnostic tool. Get an instant, honest snapshot of your readiness for the PMI Risk Management Professional (PMI-RMP) exam and identify the specific topics that need your focus.

RMP Questions

What You Get with Full Access:

Complete Question Bank

Timed Exam Simulator

Smart Performance Dashboard

Identify Weak Spots

Verified Answer & Explanations

Unlimited Reattempts

Mobile-Friendly Study

Regular Content Updates



1 Month Access

$19.99

Buy Now


12 Months Access

$49.99

Buy Now

RMP Complete Package

Choose a plan and prepare with realistic RMP test questions designed to mirror test-day conditions. Every plan includes a full PMI Risk Management Professional (PMI-RMP) practice exam questions, a timed exam simulator, performance tracking, detailed answer explanations, and the ability to reattempt questions to improve accuracy and confidence.

245 Practice Questions - Flexible Quiz Modes - Unlimited Attempts