Skip to main content

Free RMP Exam Questions That Helps Candidates Pass - Page 3

RMP Questions 21-30 of 80 free
0/10 answered · 0 correct

Choose an answer and click Check answer to see if you're right, with the full explanation.

Question 21

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks.

What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

Correct answer: D

Explanation

In a situation where there are concerns about finishing the project within the budget due to delays and cost increments, using estimation and probability analysis tools, such as Monte Carlo simul-ations, is appropriate. These tools help the risk manager to model potential outcomes based on different scenarios, providing a statistical probability of staying within the budget or finishing on time. This data-driven approach allows for more informed decision-making regarding the project's financial risks​.

 

 

Question 22

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

Correct answer: D

Explanation

Meeting with the traffic authority staff responsible for the new regulation allows the project manager and risk manager to understand the potential changes and their impact on the project. This will help them proactively address any potential issues and ensure the project complies with the new regulations.

According to the PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1, the project manager and the risk manager should handle this situation by meeting with the traffic authority staff in charge of the new regulation. This is because:

The new traffic regulation is an external risk that could affect the project objectives, such as scope, schedule, cost, quality, and customer satisfaction. External risks are those that arise from outside the project boundaries and are beyond the control of the project team. Examples of external risks include changes in government policies, regulations, laws, market conditions, environmental factors, etc.

The project manager and the risk manager should proactively engage with the external stakeholders who have the power and influence to create or modify the external risks. By meeting with the traffic authority staff, they can establish a positive relationship, gain insights into the new regulation, and influence its development to align with the project needs. They can also obtain information on the probability and impact of the risk, as well as the potential response strategies.

The other options are not effective in handling this situation because:

Ensuring the project complies with the current traffic regulations and laws does not address the risk of the new regulation that could change the project requirements, scope, or deliverables. It also does not help the project team to prepare for the possible changes and mitigate their negative effects.

Sending a letter to the traffic authority with the general project information does not establish a direct and timely communication channel with the external stakeholder. It also does not provide enough details or feedback to understand the nature and implications of the new regulation.

Performing inquiries on the website of the traffic authority weekly does not allow the project team to influence the development of the new regulation or obtain reliable and updated information. It also does not enable the project team to build trust and rapport with the external stakeholder.

PMBOK Guide, 6th edition, Chapter 11: Project Risk Management1

Risk Management Professional (PMI-RMP)® Exam Cert Guide2

Question 23

A risk manager is working on the risk management plan for a new digital platform and realizes the project sponsor, who is the IT manager, has not been invited to the project team meetings. The IT manager is concerned that the IT infrastructure is unable to host the new platform the team is creating. The risk manager asks the IT manager to be included in the meetings.

What should the IT manager's role be in the project team meetings?

Correct answer: A

Explanation

A risk owner is the person assigned to manage, monitor, and report on a specific risk. When the IT manager has unique insight or control over risks associated with IT infrastructure, they should be formally assigned as a risk owner for those risks. The PMBOK® Guide emphasizes:

“Risk owners are identified during the risk management planning process and should be engaged in relevant meetings and risk discussions. Assigning the IT manager as a risk owner ensures proper accountability for IT-related risks.”

— PMBOK® Guide, 6th Edition, Section 11.3.2.1 (Risk Register: Risk Owner)

This promotes ownership, accountability, and effective risk management.

[References:, PMBOK® Guide, 6th Edition, Section 11.3.2.1, Practice Standard for Project Risk Management, PMI, Section 5.3, , , ]

Question 24

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

Correct answer: B

Explanation

The project manager should reassess risks by conducting a new assumptions and constraints analysis. This will help identify any previously overlooked risks and ensure that the risk register is comprehensive and up-to-date.

Question 25

In a complex project, individual risks have been identified with the stakeholders. The project sponsor asks the risk manager about the likelihood of project success. Which risk analysis tool(s) should the risk manager use as a basis for their response?

Correct answer: A

Explanation

 

To assess the likelihood of project success, the risk manager should use both probabilistic and quantitative risk analyses. Probabilistic analysis helps in understanding the range of possible outcomes and their probabilities, while quantitative risk analysis provides a numerical estimate of the overall risk impact on project objectives. Combining these methods gives a more comprehensive understanding of the project’s risk profile and allows the risk manager to provide an informed response regarding the likelihood of project success. PMI’s risk management standards support the use of these tools for a thorough and accurate risk assessment​​.

 

Question 26

During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.

What should the risk manager do?

Correct answer: D

Explanation

 

When a risk triggers several other risks that need a quick response, performing a risk urgency assessment is the appropriate course of action. This assessment helps determine how soon a response is required for each risk, considering their potential impact on the project. The PMI guidelines emphasize the importance of urgency in prioritizing risk responses, particularly when the consequences could significantly affect project deliverables if not addressed promptly​.

 

Question 27

When should the benefits of quantitative risk analysis be weighed against the effort required to ensure that the additional insights and value justify the extra effort?

Correct answer: A

Explanation

The Plan Risk Management process is where the project team determines the depth and breadth of risk management activities, including whether quantitative risk analysis is appropriate. PMBOK® Guide says:

"The Plan Risk Management process determines how to approach and conduct the risk management activities for a project. This includes weighing the benefits and effort of advanced techniques such as quantitative risk analysis."

— PMBOK® Guide, 6th Edition, Section 11.1

[References:, PMBOK® Guide, 6th Edition, Section 11.1, ]

Question 28

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor's ask?

Correct answer: C

Explanation

Quantitative risk analysis helps to numerically analyze the probability and impact of risks on project objectives. By performing quantitative risk analysis, the risk manager can present the risks with the most impact on achieving the project objectives to the project sponsor. (Reference: PMBOK Guide, 6th Edition, p. 423)

According to the PMI Risk Management Professional (PMI-RMP) Reference Materials, sensitivity analysis is a type of probabilistic analysis that determines how sensitive the results of the analysis are to uncertainties in input variables. Sensitivity analysis determines which uncertainty has the greatest potential for an impact on the project objectives, such as cost, schedule, scope, or quality1. In this case, the risk manager should use sensitivity analysis to facilitate the sponsor’s ask, as it will help to identify and present the risks that have the most impact on achieving the project objectives. Sensitivity analysis can also show how the project objectives will vary with the changes in the input variables, such as the probability and impact of risks2. Sensitivity analysis can be performed using various tools and techniques, such as tornado diagrams, spider charts, or influence diagrams3.

[References: 1: PMI, A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Sixth Edition, 2017, p. 403 2: PMI, Practice Standard for Project Risk Management, 2009, p. 95 3: Quantitative Risk Analysis in Project Management - PM-Training, , ]

Question 29

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

Correct answer: D

Explanation

The stakeholders should prepare a risk-adjusted backlog when making decisions on how to respond to known and new risks. A risk-adjusted backlog helps prioritize work items based on their risk level and potential impact on the project.

 A risk-adjusted backlog is an artifact that reflects the prioritization of the product backlog items based on their risk exposure. It is used to plan for the execution phase of an agile project, where the stakeholders can decide how to respond to known and new risks by selecting the most valuable and least risky items to deliver. A risk-adjusted backlog can help the stakeholders to optimize the value delivery and reduce the uncertainty of the project outcomes. References: PMI, The Standard for Risk Management in Portfolios, Programs, and Projects, 2019, p. 113; PMI, Agile Practice Guide, 2017, p. 54.

Question 30

A project with impending risks has 12 deliverables as subprojects, which will be executed in three different locations involving multiple stakeholders. What should the risk manager do to organize the prevailing risks?

Correct answer: A

Explanation

In complex projects with multiple deliverables, locations, and stakeholders, best practice is to combine individual risk identification (e.g., interviews, surveys) with group-based methods (e.g., focus groups, workshops) to ensure comprehensive risk coverage and diverse input. According to the PMBOK® Guide:

“Both individual and group risk identification techniques are valuable. Combining interviews (individual) with facilitated workshops or focus groups (group) can help identify risks at all levels and build a comprehensive risk register for the overall project.”

— PMBOK® Guide, 6th Edition, Section 11.2.2.2 (Data Gathering: Interviews, Facilitation)

ISO 31000 also recommends a mix of approaches to ensure risks are not overlooked due to limited perspectives.

[References:, PMBOK® Guide, 6th Edition, Section 11.2.2.2, ISO 31000:2018, Section 6.4, ]
0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free RMP questions practiced · - overall accuracy

Want the full RMP question bank?

Unlock all 245 questions with mock exam, explanations for every option and domain-level analytics.

Page 3 of 8 · Questions 21-30 of 80 free

PracticeTestMaster is an independent exam prep provider. RMP is the property of PMI.

Full access

Unlock all 245 RMP questions

You're practicing 80 free questions. Paid plans add:

  • 165 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your RMP progress

Questions answered0
Accuracy-

Saved on this device.

RMP exam overview

Exam
PMI Risk Management Professional (PMI-RMP)
Code
RMP
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 245 questionsFrom $19.99
Unlock