Timed Practice Tests for Nursing, Construction, Finance, Career, Education & Skilled Trade Exams
Question # 11

During a project team meeting, a risk manager realizes that the initial assumptions on the project schedule are too optimistic. The risk manager believes that the project might not meet its deadline as initially stated.

What is the reason for misunderstanding the assumptions from the beginning?

Options:

A.

Government regulations have changed in the last week, and now additional approval processes are required.

B.

The team's compensation was reduced and they lost the motivation to comply with the project deadline.

C.

The stakeholders prepared the initial schedule assumptions based only on the results of the last project.

D.

The sponsor had neither presented the actual results to the stakeholders nor updated the initial assumptions.

Question # 12

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

Options:

A.

Invite these stakeholders to regular meetings to engage them in the definition of project assumptions.

B.

Identify new stakeholders who might replace those involved thus far and are more closely aligned to the project goals.

C.

Review the risk thresholds to potentially accommodate the concerns raised by these stakeholders.

D.

Perform a stakeholder analysis to determine their interests and how they should be taken into account. 

Question # 13

A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.

What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)

Options:

A.

Scope of work and requirements

B.

Monte Carlo analysis from a similar project

C.

List of pre-approved contractors

D.

Organization chart for city permit department

E.

Risk management plan

Question # 14

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

Options:

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted. 

Question # 15

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Viewing page 3 out of 15 pages

Try free RMP sample questions and upgrade to complete 245 questions bank & timed simulator.

RMP Practice Test Main Page

Don't just take our word for it. Industry research shows that targeted RMP certification practice questions MCQs dramatically increases pass rates for the PMI Risk Management Professional (PMI-RMP). Our platform is built on this principle, offering the most realistic simulations available to give you that proven advantage.


RMP Overview

Name PMI Risk Management Professional (PMI-RMP)
Code RMP
Vendor Professional
Certification PMI

Our free RMP exam questions sample is your personalized diagnostic tool. Get an instant, honest snapshot of your readiness for the PMI Risk Management Professional (PMI-RMP) exam and identify the specific topics that need your focus.

RMP Questions

What You Get with Full Access:

Complete Question Bank

Timed Exam Simulator

Smart Performance Dashboard

Identify Weak Spots

Verified Answer & Explanations

Unlimited Reattempts

Mobile-Friendly Study

Regular Content Updates



1 Month Access

$19.99

Buy Now


12 Months Access

$49.99

Buy Now

RMP Complete Package

Choose a plan and prepare with realistic RMP test questions designed to mirror test-day conditions. Every plan includes a full PMI Risk Management Professional (PMI-RMP) practice exam questions, a timed exam simulator, performance tracking, detailed answer explanations, and the ability to reattempt questions to improve accuracy and confidence.

245 Practice Questions - Flexible Quiz Modes - Unlimited Attempts