Question 71
During execution, a risk response plan is triggered. What should the project manager do?
Explanation
Process domain requires monitoring and controlling risks. When a trigger occurs, execute planned responses, update documentation, and reassess residual risks. A and C neglect proactive management, D abdicates responsibility.