Free PMP Exam Questions That Helps Candidates Pass - Page 2

PMP Questions 11-20 of 80 free
0/10 answered · 0 correct

Choose an answer and click Check answer to see if you're right, with the full explanation.

Question 11

A new stakeholder challenges the project scope late in execution. What should the project manager do?

Correct answer: B

Explanation

People domain emphasizes stakeholder engagement. Considering input respectfully while applying change control balances governance and relationships.

Question 12

Your project is nearing completion, but leadership decides to pivot strategy away from your project’s deliverables. What is the best step?

Correct answer: B

Explanation

Business Environment stresses alignment with organizational strategy. B ensures informed decision-making on whether to terminate, redirect, or adapt. A and D waste resources, C skips governance.

Question 13

A client requests a feature that violates industry compliance standards. What should the project manager do?

Correct answer: B

Explanation

Business Environment requires compliance. Negotiating alternatives balances client needs with regulatory obligations. A and D risk violations, C is rigid.

Question 14

A risk event occurs and was not in the original risk register. What should the project manager do?

Correct answer: B

Explanation

Process domain stresses continuous risk management. New risks require documentation and corrective action. A and C abdicate responsibility, D is extreme.

Question 15

During execution, you find that several deliverables are incomplete but marked “done.” What should the project manager do?

Correct answer: B

Explanation

Process domain emphasizes scope validation and quality assurance. Enforcing acceptance criteria ensures integrity of deliverables. A and D waste resources, C escalates too early.

Question 16

Remote team members feel disconnected from on-site colleagues. What should the project manager do?

Correct answer: B

Explanation

People domain emphasizes inclusivity and engagement. Virtual team-building fosters collaboration and morale. A and C dismiss inclusivity, D wastes talent.

Question 17

A senior stakeholder consistently bypasses the project manager and gives direct instructions to the team. What should the project manager do?

Correct answer: B

Explanation

People domain stresses stakeholder management and communication clarity. Redirecting instructions maintains governance and reduces confusion. A, C, and D create disruption or avoidance.

Question 18

Cost performance index (CPI) = 1.05, schedule performance index (SPI) = 0.95. What does this mean?

Correct answer: B

Explanation

CPI > 1 indicates under budget; SPI < 1 indicates behind schedule. The Process domain expects corrective action for schedule inefficiency.

Question 19

Two departments have competing resource demands, delaying project work. What should the project manager do?

Correct answer: B

Explanation

People domain requires negotiation and conflict resolution. The PM should engage stakeholders to align priorities. A bypasses collaboration, C escalates prematurely, D abdicates responsibility. B demonstrates leadership and balanced stakeholder engagement.

Question 20

During retrospectives, the team hesitates to discuss problems openly. What should the project manager do?

Correct answer: B

Explanation

People domain emphasizes psychological safety and open communication. Blame-free culture promotes transparency and improvement. A and C discourage collaboration, D misinterprets silence.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free PMP questions practiced · - overall accuracy

Want the full PMP question bank?

Unlock all 288 questions with mock exam, explanations for every option and domain-level analytics.

Page 2 of 8 · Questions 11-20 of 80 free

PracticeTestMaster is an independent exam prep provider. PMP is the property of Project Management Institute (PMI).

Full access

Unlock all 288 PMP questions

You're practicing 80 free questions. Paid plans add:

  • 208 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your PMP progress

Questions answered0
Accuracy-

Saved on this device.

PMP exam overview

Exam
Project Management Professional
Code
PMP
Category
Business
Credential body
Project Management Institute (PMI)
Updated
Nov 27, 2026