Skip to main content

Free PMP Exam Questions That Helps Candidates Pass - Page 7

PMP Questions 61-70 of 80 free
0/10 answered · 0 correct

Choose an answer and click Check answer to see if you're right, with the full explanation.

Question 61

During execution, scope creep has increased costs significantly. What should the project manager do?

Correct answer: B

Explanation

Process domain emphasizes scope and cost management. Formal change control realigns baselines. A and C bypass governance, D damages relationships.

Question 62

Project reports show multiple open issues unresolved for weeks. What should the project manager do?

Correct answer: B

Explanation

Process domain highlights disciplined issue management. Assigning ownership and tracking ensures accountability. A and D neglect governance, C escalates unnecessarily.

Question 63

The team complains of information overload from too many reports. What should the project manager do?

Correct answer: B

Explanation

People domain highlights effective communication. Tailoring reports ensures relevance without overloading the team. A and D reduce transparency, C ignores concerns.

Question 64

Your project is aligned with corporate sustainability goals. Midway, the sponsor asks you to cut cost by eliminating sustainability-related features. What should you do?

Correct answer: B

Explanation

Business Environment requires alignment with organizational strategy. Eliminating features without analysis may misalign with corporate objectives. A disregards strategy, C ignores stakeholder needs, D postpones critical discussion. B ensures alignment and informed decision-making.

Question 65

Team conflicts are consuming time and reducing productivity. What should the project manager do?

Correct answer: B

Explanation

People domain stresses leadership and conflict resolution. Facilitating resolution builds trust and restores productivity. A ignores issues, C and D escalate unnecessarily.

Question 66

A supplier misses a critical delivery date on the critical path. What should the project manager do next?

Correct answer: B

Explanation

The Process domain expects disciplined issue and schedule management. The PM should document the issue, quantify impact (network analysis), evaluate options (expedite, alternative sourcing, fast-track), and process changes via change control. A may be premature; C is drastic without analysis; D may waste cost and not address root cause. B reflects analyze-then-act.

Question 67

While closing the project, the client requests additional features to be added. What should the project manager do?

Correct answer: B

Explanation

Business Environment requires governance and benefit alignment. Scope cannot be changed at closure; additional features must be managed as a new project or through formal change control. A is rigid, C causes unauthorized work, D delays closure. B ensures compliance and client satisfaction.

Question 68

A project requires multiple vendor deliverables that are interdependent. What should the project manager do to manage risks?

Correct answer: B

Explanation

Process domain emphasizes integrated planning. Managing dependencies through an integrated schedule ensures visibility and proactive risk management.

Question 69

A deliverable fails to meet quality standards during inspection. What should the project manager do?

Correct answer: B

Explanation

Process domain emphasizes quality assurance. Recording issues, analyzing causes, and implementing corrective action ensures long-term improvement. A focuses only on rework, C neglects quality, D escalates prematurely.

Question 70

The government introduces subsidies for green projects. How should the project manager respond?

Correct answer: B

Explanation

Business Environment focuses on maximizing benefits and strategic alignment. Ignoring or delaying risks losing opportunities. B ensures the project leverages external factors for greater ROI.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free PMP questions practiced · - overall accuracy

Want the full PMP question bank?

Unlock all 288 questions with mock exam, explanations for every option and domain-level analytics.

Page 7 of 8 · Questions 61-70 of 80 free

PracticeTestMaster is an independent exam prep provider. PMP is the property of Project Management Institute (PMI).

Full access

Unlock all 288 PMP questions

You're practicing 80 free questions. Paid plans add:

  • 208 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your PMP progress

Questions answered0
Accuracy-

Saved on this device.

PMP exam overview

Exam
Project Management Professional
Code
PMP
Category
Business
Credential body
Project Management Institute (PMI)
Updated
Nov 27, 2026
Unlock all 288 questionsFrom $19.99
Unlock