Question 61
Which estimating technique uses a statistical relationship between historical data and variables (e.g., cost per meter, hours per feature) to compute estimates?
Explanation
Parametric estimating applies equations derived from historical data to estimate effort, duration, or cost based on key drivers (e.g., units of output, size, complexity). Examples include $/square meter for construction, story points-to-hours conversion factors in well-calibrated contexts, or function points for software. When models are valid and inputs are reliable, parametrics yield scalable, repeatable estimates and support sensitivity analysis. Analogous estimating (Option A) leverages expert judgment using actuals from similar past projects—fast but less precise. Bottom-up (Option B) decomposes work to the lowest practical level and aggregates estimates—accurate but time-consuming. Three-point (Option D) addresses uncertainty by combining optimistic, most-likely, and pessimistic values (PERT or triangular). CAPM predictive planning encourages using historical data, adjusting for complexity, and combining methods where appropriate. With parametrics, teams should validate model assumptions, continuously refine factors with actuals, and document the basis of estimate to support transparency and future lessons learned.