Question 61

Which estimating technique uses a statistical relationship between historical data and variables (e.g., cost per meter, hours per feature) to compute estimates?

Correct answer: C

Explanation

Parametric estimating applies equations derived from historical data to estimate effort, duration, or cost based on key drivers (e.g., units of output, size, complexity). Examples include $/square meter for construction, story points-to-hours conversion factors in well-calibrated contexts, or function points for software. When models are valid and inputs are reliable, parametrics yield scalable, repeatable estimates and support sensitivity analysis. Analogous estimating (Option A) leverages expert judgment using actuals from similar past projects—fast but less precise. Bottom-up (Option B) decomposes work to the lowest practical level and aggregates estimates—accurate but time-consuming. Three-point (Option D) addresses uncertainty by combining optimistic, most-likely, and pessimistic values (PERT or triangular). CAPM predictive planning encourages using historical data, adjusting for complexity, and combining methods where appropriate. With parametrics, teams should validate model assumptions, continuously refine factors with actuals, and document the basis of estimate to support transparency and future lessons learned.

Question 62

Which artifact is primarily used to decompose and define total project scope into manageable components?

Correct answer: B

Explanation

In predictive planning, scope management centers on progressively elaborating and decomposing the project’s deliverables and work. The Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to accomplish project objectives and create required deliverables. The CAPM blueprint highlights the scope baseline—comprising the scope statement, WBS, and WBS dictionary—as the reference for planning, executing, and controlling scope. By breaking work into work packages, the WBS creates clear units for estimating cost and duration, assigning responsibility, and monitoring performance. The Requirements Traceability Matrix (Option A) links requirements to origins and deliverables for validation, but it does not decompose work. The Responsibility Assignment Matrix (Option C), such as a RACI, maps roles to tasks after the work has been defined. A Product Roadmap (Option D) provides a time-phased view of features and releases, more common in adaptive or product-oriented planning, but is not the formal decomposition tool for predictive scope planning. Using the WBS properly reduces scope creep, aligns stakeholders, and lays the foundation for schedule network development, estimation, and performance measurement.

Question 63

Your team’s Cumulative Flow Diagram shows the “In Review” band widening over the last three sprints while “Done” lags. What is the BEST first action?

Correct answer: B

Explanation

A widening band in a CFD signals accumulating work in that state—“In Review” is a bottleneck. The first step is to cap WIP at that column and swarm to finish items to “Done.” Analyze root causes: unclear review policies, insufficient reviewers, large batch sizes, or long feedback loops. Tightening the Definition of Done (e.g., pairing, peer reviews earlier) and automating checks can reduce review load. Option A increases WIP, worsening cycle time and context switching. Option C treats symptoms and risks burnout without fixing systemic flow issues. Option D (splitting after development) is an anti-pattern that hides work and undermines vertical slicing; instead split earlier so items are reviewable in smaller increments. CAPM’s agile content stresses managing flow by limiting WIP, making policies explicit, and inspecting/adapting with data. Track lead time and throughput before/after the change to validate improvement, and maintain stable quality by ensuring reviews verify acceptance criteria and the Definition of Done.

Question 64

Your organization uses phase gates (“kill points”). What is the PRIMARY purpose of a phase gate review?

Correct answer: B

Explanation

Phase gates are governance checkpoints where executives and key stakeholders review performance, risks, compliance, and updated forecasts to determine go/no-go/hold decisions. The goal is to ensure the initiative still aligns with strategy and the business case before committing further resources. Option A confuses gating with transition to operations, which may or may not occur at a gate. Option C prescribes a one-size-fits-all deliverable; gates are tailored by lifecycle and industry—design finalization may be a criterion in some contexts but is not universal. Option D is not a standard gate outcome. CAPM fundamentals emphasize tailoring governance: define entry/exit criteria, required artifacts (e.g., updated benefits forecast, risk profile), and decision rights. Effective gates increase portfolio discipline—failing fast when needed, redirecting scope, or adding controls. They also clarify expectations for teams, reducing churn by aligning on what “readiness” looks like before moving forward.

Question 65

Under which circumstance is it MOST appropriate for a Product Owner to cancel a sprint?

Correct answer: B

Explanation

Scrum allows the Product Owner to cancel a sprint if the Sprint Goal no longer makes sense—typically because of market shifts, regulatory change, or a strategic pivot that renders the current goal obsolete. Cancellation protects value by avoiding sunk cost on work that no longer advances the Product Goal. A dip in velocity (Option A) is not a reason to cancel; velocity varies and the team adapts its plan to still meet the Sprint Goal. A critical bug (Option C) can be handled by re-planning within the sprint or swapping scope, provided the Sprint Goal remains achievable. Excess stakeholder requests (Option D) are addressed by backlog ordering and negotiation; they don’t invalidate the goal. If cancellation occurs, any completed items meeting the Definition of Done may be reviewed and potentially released. The team then quickly plans a new sprint oriented around the revised goal. CAPM candidates should recognize that cancellation is rare and costly; it should follow a deliberate decision about value, not short-term discomfort.

Question 66

Which set BEST represents the outcomes of Sprint Planning?

Correct answer: B

Explanation

Sprint Planning answers three questions: Why is this sprint valuable? (Sprint Goal), What can be done this sprint? (selected PBIs), and How will the chosen work get done? (a plan forming the Sprint Backlog). The Developers create the plan, frequently decomposing PBIs into emergent tasks and identifying collaboration/WIP policies needed to meet the goal. Assigning tasks to individuals up front (Option A) undermines self-management and adaptability. A fixed scope contract with sign-off (Option C) conflicts with empiricism; the plan can evolve as the team learns, provided the goal remains intact. Velocity targets and personal objectives (Option D) distract from team outcomes and can drive gaming. CAPM’s agile focus is on outcome-oriented goals, transparency of the plan, and collaboration. The result of Sprint Planning should be a clear goal, an understood scope, and a realistic plan aligned to capacity and the Definition of Done, setting the team up for a predictable, value-focused sprint.

Question 67

A Kanban team has a historical throughput of 5 items/day and an average cycle time of 4 days. What is the expected average WIP by Little’s Law?

Correct answer: D

Explanation

Little’s Law states: WIP = Throughput × Cycle Time (with consistent units and a stable system). Here, throughput = 5 items/day and cycle time = 4 days → WIP = 5 × 4 = 20 items. This provides a reality check on system capacity: if the team routinely sees 35 items in progress, the law predicts longer cycle times or lower throughput until the system stabilizes. CAPM’s agile content stresses managing flow by limiting WIP, making policies explicit, and using flow metrics to guide improvement. If WIP is materially higher than 20, introduce explicit WIP limits, reduce batch sizes, and finish work before starting more. If throughput or cycle time shifts (e.g., new tech, staffing), recompute expectations and adjust limits. Little’s Law is descriptive, not prescriptive; treat it as a guardrail to set realistic service-level expectations and to detect when the system is overloaded. Pair it with a cumulative flow diagram and lead-time distributions to diagnose bottlenecks (“In Review” queues) and stabilize delivery predictability.

Question 68

Who is accountable for ordering the Product Backlog, and what factors typically influence that ordering?

Correct answer: B

Explanation

The Product Owner (PO) is accountable for maximizing product value by ordering the Product Backlog. Ordering reflects economic and strategic considerations—user/business value, risk reduction/opportunity enablement, time criticality (deadlines/seasonality), dependencies, and feedback from stakeholders and telemetry. Technical considerations are vital, but they inform the PO’s decisions rather than replace them. The Scrum Master (Option A) coaches process and removes impediments; they don’t order backlog. Developers (Option C) estimate and advise on feasibility and risk; unilateral technical ordering can misalign with business goals. Sponsors (Option D) influence strategy, but single-factor budget timing is insufficient. CAPM’s agile domain stresses transparency and collaboration: shared refinement sessions, explicit ordering criteria, and evidence-based techniques (e.g., WSJF, hypothesis tracking) keep the backlog coherent. Good practice includes regularly inspecting outcomes at Sprint Reviews and adjusting ordering to reflect learning, enabling faster time-to-value and reduced waste.

Question 69

You use three-point estimating on a task with Optimistic = 10 days, Most Likely = 14 days, Pessimistic = 22 days. What is the PERT expected duration?

Correct answer: B

Explanation

The PERT weighted average emphasizes the Most Likely value to reflect typical outcomes while acknowledging uncertainty. The formula is (O + 4M + P) / 6. Substituting the values: (10 + 4×14 + 22) / 6 = (10 + 56 + 22) / 6 = 88 / 6 ≈ 14.67 days, commonly rounded to 14.7 days. This expected duration feeds schedule network analysis and risk-aware forecasting. Teams may also compute variance: ((P − O) / 6)² = (12/6)² = 2² = 4, enabling aggregation of uncertainty across paths to analyze schedule risk. While simple, three-point estimates reduce bias compared to single-point estimates and help identify activities with high uncertainty for targeted risk responses (contingency, buffers, alternative strategies). CAPM candidates should also distinguish PERT from triangular distributions (equal weights) and understand when to refine inputs via expert judgment, historical data, or parametric models. After calculation, validate whether the activity lies on or near the critical path, since uncertainty there has disproportionate impact on the project completion date.

Question 70

Which activity belongs to Develop Team (Team Development) rather than Manage Team (Team Management)?

Correct answer: B

Explanation

Develop Team focuses on improving competencies, team interaction, and overall team environment to enhance project performance—activities like training, coaching, team-building, recognition, and developmental feedback. Conducting a skills gap analysis and arranging training squarely fits this process. Manage Team, by contrast, is about tracking performance, providing corrective feedback, resolving conflicts, and issue handling. Mediation (Option A), documenting/escalating performance issues (Option C), and formal discipline (Option D) are Manage Team (and HR) actions. CAPM fundamentals highlight that high-performing teams don’t happen by accident: the Project Management Plan should include a Resource Management Plan with strategies for acquisition, development, and recognition. Development investments reduce defects, improve throughput, and mitigate risks associated with specialized roles. Continual evaluation (e.g., team health checks, retrospectives) informs which development actions are most impactful. Recognition programs aligned to project goals further reinforce desired behaviors and outcomes.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free CAPM questions practiced · - overall accuracy

Want the full CAPM question bank?

Unlock all 268 questions with mock exam, explanations for every option and domain-level analytics.

Page 7 of 8 · Questions 61-70 of 80 free

PracticeTestMaster is an independent exam prep provider. CAPM is the property of PMI.

Full access

Unlock all 268 CAPM questions

You're practicing 80 free questions. Paid plans add:

  • 188 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your CAPM progress

Questions answered0
Accuracy-

Saved on this device.

CAPM exam overview

Exam
Certified Associate in Project Management
Code
CAPM
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 268 questionsFrom $19.99
Unlock