Question 51

Given EV = $600k, AC = $550k, PV = $650k, which interpretation is MOST accurate?

Correct answer: B

Explanation

Compute variances and indices. Cost Variance (CV) = EV − AC = 600 − 550 = +$50k (positive is good → under budget). Schedule Variance (SV) = EV − PV = 600 − 650 = −$50k (negative → behind schedule). Cost Performance Index (CPI) = EV/AC = 600/550 ≈ 1.09 (earning $1.09 per $1 spent), and Schedule Performance Index (SPI) = EV/PV = 600/650 ≈ 0.92 (progressing at ~92% of planned rate). Therefore the project is under budget but behind schedule—Option B. CAPM EVM objectives include interpreting these signals to drive action: analyze drivers of favorable cost (e.g., lower rates, deferred work) and unfavorable schedule (bottlenecks, underestimated tasks, dependency delays). Consider targeted interventions on the critical path (e.g., fast tracking, focused crashing with business cases) while protecting quality. Communicate impacts via forecasts (e.g., EAC using BAC/CPI if trends persist) and update the risk register with schedule-related threats (overtime fatigue, morale) and opportunities (process improvements). Transparent reporting enables informed decisions on trade-offs among scope, time, cost, and risk.

Question 52

Given BAC = 1,000,000; EV = 400,000; AC = 500,000. If management insists on meeting the original BAC, what is the To-Complete Performance Index (TCPI) relative to BAC?

Correct answer: C

Explanation

TCPI (to meet BAC) = (BAC − EV) ÷ (BAC − AC). Substituting: (1,000,000 − 400,000) ÷ (1,000,000 − 500,000) = 600,000 ÷ 500,000 = 1.20. A TCPI of 1.20 means the remaining work must be accomplished at 20% better cost efficiency than the project has achieved to date (CPI so far = EV/AC = 0.80). This is a challenging target and signals the need for strong corrective action: tighten change control, address drivers of inefficiency (rework, supplier performance, resource mix), and consider trade-offs in scope, quality, or schedule. If leadership instead approves a revised EAC, the alternative formula TCPI(EAC) = (BAC − EV) ÷ (EAC − AC) applies, which usually yields a lower (more achievable) index. CAPM EVM objectives require interpreting indices, selecting appropriate forecasts, and communicating implications transparently so stakeholders understand feasibility and risk of recovery plans before committing to them.

Question 53

A novel algorithm may violate safety regulations if it behaves unpredictably. The team proposes using a certified off-the-shelf module instead, removing the risk entirely. Which threat response is this?

Correct answer: C

Explanation

Risk avoidance changes the plan to eliminate the threat or protect the project from its impact. Replacing a risky custom algorithm with a certified module removes the hazardous activity, thereby avoiding the regulatory non-compliance risk altogether. Mitigation (Option A) would reduce probability or impact (e.g., more testing, fail-safes) but still proceed. Transfer (Option B) shifts financial consequences (e.g., insurance, fixed-price contracts) but does not remove the underlying technical risk. Acceptance (Option D) acknowledges the risk with minimal action beyond reserves or monitoring. CAPM risk management stresses selecting responses aligned with risk appetite, cost-benefit, and constraints. Avoidance often affects scope, cost, or schedule and thus requires integrated change control and stakeholder alignment. Even when avoiding, add secondary risks to the register (e.g., vendor lock-in, integration constraints, licensing limits) and define validation steps to confirm the new module meets performance and security NFRs. Clear traceability supports audits and formal acceptance, especially in regulated domains.

Question 54

Which contract type places the GREATEST cost risk on the seller and provides the most cost predictability for the buyer?

Correct answer: C

Explanation

In procurement planning, risk allocation is a key consideration. Firm Fixed Price (FFP) contracts lock in a total price for a defined scope, placing most cost risk on the seller. If actual costs exceed expectations, the seller absorbs the overrun, creating strong incentives for efficiency and scope clarity. For the buyer, FFP offers high cost predictability and simpler administration once scope is baselined. CPFF (Option A) reimburses allowable costs plus a fixed fee; the buyer bears most cost risk and must exercise tighter oversight. T&M (Option B) blends fixed rates with variable quantities; risk is shared, and buyer exposure increases with poor control of hours or materials. CPIF (Option D) adds incentives to align performance, but the buyer still reimburses costs, keeping significant risk. CAPM objectives stress selecting contract types consistent with scope maturity, market conditions, and risk appetite. With FFP, invest in thorough requirements, a robust WBS, and clear acceptance criteria to avoid disputes, and pair with effective change control to manage any needed adjustments.

Question 55

Which statement BEST describes Product Backlog refinement?

Correct answer: B

Explanation

Backlog refinement (a.k.a. grooming) is a continuous, collaborative activity where the Product Owner and Developers discuss upcoming items, clarify acceptance criteria, split epics into smaller stories, assess dependencies, and estimate effort (often with relative sizing). It improves readiness for Sprint Planning and stabilizes forecasting by reducing uncertainty. It is not a formal Scrum event with a fixed timebox (Option A), though teams often allocate a reasonable portion of capacity (e.g., up to ~10%) to refinement. Option C reframes refinement as management approval, which conflicts with agile empowerment and value-driven ordering. Option D misassigns ownership; while the Product Owner is accountable for ordering and ensuring value, the Developers estimate and advise on feasibility and risks. CAPM’s agile content highlights that effective refinement increases flow predictability, reduces mid-sprint churn, and aligns stakeholders on “Definition of Ready” expectations. Good practices include using examples, DoR checklists, and slicing techniques (e.g., vertical thin slices) to ensure items are implementable within a sprint and meet the team’s Definition of Done when completed.

Question 56

A team wants to visualize work-in-progress, identify bottlenecks, and observe flow stability over time. Which artifact is MOST appropriate?

Correct answer: B

Explanation

A Cumulative Flow Diagram (CFD) displays the count of work items in each workflow state over time, revealing WIP levels, arrival and departure rates, and queue buildups that indicate bottlenecks. Stable, parallel bands suggest predictable flow; widening of a band highlights accumulation in that state and prompts investigation. Burndown charts (Option A) show remaining work in a timebox but do not expose per-state accumulation or systemic bottlenecks. Velocity charts (Option C) summarize completed work per iteration, useful for forecasting but not diagnosing flow constraints. A product roadmap (Option D) communicates sequencing and releases at a higher level rather than operational flow. CAPM agile objectives emphasize limiting WIP, managing cycle time, and using empirical data to improve throughput. Teams can combine CFD insights with explicit WIP limits and policies to balance demand and capacity, then run small experiments (e.g., adjust WIP limits, rebalance skills, address blockers) and measure impacts on lead and cycle times. This fosters continuous improvement and predictable delivery, aligning with agile principles and stakeholder expectations.

Question 57

Which statement correctly distinguishes total float from schedule reserve?

Correct answer: C

Explanation

Total float (TF) is the amount an activity or path can slip without delaying the project finish (or a key milestone), computed via forward/backward passes on the schedule network. It emerges from logic relationships and durations; activities on the critical path have TF ≈ 0. Schedule reserve (sometimes called management reserve for time) is an explicit buffer added at higher levels—e.g., at the end of a phase or release—to protect delivery dates from residual uncertainty. Consuming schedule reserve typically requires governance approval because it changes the forecasted finish relative to the baseline. Option A is incorrect because their origins and controls differ. Option B reverses roles. Option D misattributes ownership. CAPM scheduling emphasizes transparent modeling: use TF to optimize sequencing and resource allocation; use schedule reserve to handle residual, systemic risks identified in risk planning. Both should be visible: TF in the schedule model, reserves in management plans and status reports, ensuring stakeholders understand true schedule health and the remaining protective capacity.

Question 58

Which attribute is NOT part of the INVEST guideline for well-formed user stories?

Correct answer: D

Explanation

INVEST stands for Independent, Negotiable, Valuable, Estimable, Small, and Testable. These characteristics help teams craft stories that flow smoothly through refinement and delivery. Independence reduces cross-story coupling; negotiability preserves collaborative scope shaping; value focuses on outcomes for users or stakeholders; estimability supports forecasting; “small” promotes completion within a sprint; and testability ensures clear acceptance criteria and verification. “Extensible” is not part of INVEST—while designing for extensibility can be good engineering practice, it is not a user-story quality criterion and can encourage premature generalization (“gold-plating”). CAPM’s agile coverage emphasizes thin vertical slices that satisfy value and testability within the team’s Definition of Done. Applying INVEST during refinement uncovers ambiguities, hidden dependencies, and oversized work, enabling better ordering by value and risk (e.g., via WSJF). Pair INVEST with clear acceptance criteria (e.g., Given-When-Then) and a shared Definition of Ready to stabilize Sprint Planning inputs and improve predictability.

Question 59

Multiple Scrum teams deliver to a single product. To maintain consistent quality and integration, what is the BEST practice?

Correct answer: B

Explanation

A shared, product-level Definition of Done (DoD) ensures every team produces increments that are compatible, integrated, and potentially releasable at the end of each sprint. Incorporating integration, security checks, and end-to-end tests into the DoD—enforced by automated pipelines (CI)—prevents accumulation of integration risk. Option A fragments quality standards and invites “works on my machine” issues. Option C defers discovery of defects to the end, creating big-bang surprises and rework. Option D increases divergence and elongates feedback loops, undermining agility. CAPM’s agile coverage stresses built-in quality, empiricism, and frequent inspection/adaptation. Multi-team practices often include a shared backlog, cross-team refinement, dependency boards, and a Scrum-of-Scrums (or similar) for coordination. Investing in CI/CD, version control strategies (e.g., trunk-based development), and test automation shortens cycle time, increases confidence, and supports on-demand releases, aligning delivery with business priorities.

Question 60

A support team faces unpredictable arrival of work items and wants to visualize flow, limit WIP, and reduce cycle time. Which approach fits BEST?

Correct answer: B

Explanation

The CAPM agile domain expects candidates to select frameworks based on context. Kanban is well-suited to environments with variable incoming work, such as operations and support, because it emphasizes workflow visualization, explicit work-in-progress (WIP) limits, pull-based scheduling, and continuous delivery. These practices reveal bottlenecks, stabilize flow, and reduce cycle time through incremental improvements. Scrum (Option A) organizes work into timeboxed sprints with fixed goals; it’s powerful for product development but less optimal when arrival rates are unpredictable and items must be addressed as they come. Extreme Programming (Option C) offers valuable engineering practices but does not, by itself, provide a flow-based system for variable demand. Hybrid stage-gated approaches (Option D) reintroduce fixed phases and queueing that can exacerbate wait times. Implementing Kanban begins with mapping the workflow, setting initial WIP limits per column, measuring lead and cycle time, and using cadence-based reviews (e.g., replenishment, operations reviews) to tune policies. This complements service-level expectations and fosters transparency and continuous improvement, aligning tightly with agile principles of flow and value delivery.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free CAPM questions practiced · - overall accuracy

Want the full CAPM question bank?

Unlock all 268 questions with mock exam, explanations for every option and domain-level analytics.

Page 6 of 8 · Questions 51-60 of 80 free

PracticeTestMaster is an independent exam prep provider. CAPM is the property of PMI.

Full access

Unlock all 268 CAPM questions

You're practicing 80 free questions. Paid plans add:

  • 188 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your CAPM progress

Questions answered0
Accuracy-

Saved on this device.

CAPM exam overview

Exam
Certified Associate in Project Management
Code
CAPM
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 268 questionsFrom $19.99
Unlock