Question 51
Given EV = $600k, AC = $550k, PV = $650k, which interpretation is MOST accurate?
Explanation
Compute variances and indices. Cost Variance (CV) = EV − AC = 600 − 550 = +$50k (positive is good → under budget). Schedule Variance (SV) = EV − PV = 600 − 650 = −$50k (negative → behind schedule). Cost Performance Index (CPI) = EV/AC = 600/550 ≈ 1.09 (earning $1.09 per $1 spent), and Schedule Performance Index (SPI) = EV/PV = 600/650 ≈ 0.92 (progressing at ~92% of planned rate). Therefore the project is under budget but behind schedule—Option B. CAPM EVM objectives include interpreting these signals to drive action: analyze drivers of favorable cost (e.g., lower rates, deferred work) and unfavorable schedule (bottlenecks, underestimated tasks, dependency delays). Consider targeted interventions on the critical path (e.g., fast tracking, focused crashing with business cases) while protecting quality. Communicate impacts via forecasts (e.g., EAC using BAC/CPI if trends persist) and update the risk register with schedule-related threats (overtime fatigue, morale) and opportunities (process improvements). Transparent reporting enables informed decisions on trade-offs among scope, time, cost, and risk.