Question 41

Mid-sprint, a line manager bypasses the Product Owner and assigns two Developers “urgent” work. What is the BEST action for the Scrum Master?

Correct answer: C

Explanation

Scrum optimizes for focus and value via a clear Sprint Goal and an ordered Product Backlog. Work intake during a sprint flows through the Product Owner (PO); Developers then decide how to adapt their plan. The Scrum Master (SM) serves the organization by coaching stakeholders on proper interfaces, removing impediments, and protecting empiricism. The best action is to redirect the request through the PO, assess its impact on the Sprint Goal, and—if still achievable—allow Developers and the PO to renegotiate scope by trading items. If the goal becomes obsolete, the PO may cancel the sprint. Directing Developers to comply (Option A) undermines accountability and predictability. Escalating for “discipline” (Option B) is heavy-handed and often unnecessary; education and facilitation usually solve the systemic intake problem. Replacing the Sprint Goal (Option D) breaks transparency and weakens outcome focus. CAPM’s agile domain stresses stable interfaces, role clarity, and protecting the Definition of Done and flow metrics. Establishing intake policies and visualizing unplanned work helps prevent recurrence and maintains stakeholder trust.

Question 42

Stakeholders have conflicting requirements for the same report layout. What is the MOST appropriate technique to surface assumptions, negotiate trade-offs, and reach alignment quickly?

Correct answer: B

Explanation

Facilitated workshops (e.g., JAD) bring key stakeholders and delivery team members together to co-create and reconcile requirements in real time. Skilled facilitation, visual modeling (draft mockups), and decision frameworks (e.g., weighted scoring, MoSCoW) help expose assumptions, constraints, and dependencies. This approach reduces the ping-pong of asynchronous feedback and builds shared ownership in the outcome. Interviews (Option A) are valuable to gather perspectives but can entrench differences without direct negotiation. Surveys (Option C) can be efficient for broad input but are poor for resolving nuanced conflicts or validating feasibility. Defaulting to the most senior voice (Option D) risks suboptimal design and stakeholder dissatisfaction and contradicts collaborative principles emphasized in CAPM. Workshops should produce tangible artifacts—agreed acceptance criteria, a prototype, and decision logs—feeding the Requirements Traceability Matrix and backlog. Establish rules of engagement, define success criteria upfront, and timebox discussions. Document any open issues and assign owners to close them, ensuring traceability and preventing later scope disputes.

Question 43

Which procurement process manages relationships, measures performance, handles changes/claims, and closes contracts as appropriate during execution?

Correct answer: C

Explanation

Control Procurements is performed throughout execution to ensure sellers meet contractual obligations. Activities include reviewing work performance, approving invoices, managing changes via contract change control systems, addressing claims/disputes, and documenting procurement-related lessons. Plan Procurement Management (Option A) determines what to buy, contract types, and evaluation criteria. Conduct Procurements (Option B) involves obtaining seller responses, selecting sellers, and awarding contracts. Close Project or Phase (Option D) finalizes all activities, but procurement closure steps are handled within Control Procurements as contracts complete. CAPM fundamentals highlight the importance of clear acceptance criteria, performance metrics, and communication protocols defined in the contract. Effective control reduces cost/schedule risk, ensures quality, and creates an auditable trail. When issues arise, early engagement, documented notices, and structured negotiation help resolve claims before escalation to formal dispute mechanisms (e.g., ADR, arbitration).

Question 44

Your CPI is unreliable because several large change requests were just approved and re-estimation of the remaining work is underway. Which EAC method is MOST appropriate?

Correct answer: C

Explanation

Estimate at Completion (EAC) should reflect how the future will actually be executed, not merely extrapolate past performance. When significant scope changes or major re-estimations occur, historic cost efficiency (CPI) is a poor predictor for the remaining work. In such cases, PMI guidance favors a bottom-up Estimate to Complete (ETC): re-assess the unfinished scope at the current rates, methods, and resource plan, then compute EAC = AC + Bottom-Up ETC. Option A (BAC/CPI) assumes past cost performance will persist—reasonable only when the work mix and conditions remain similar. Option B (AC + (BAC − EV)) assumes the remaining work will be completed as originally planned (i.e., CPIfuture = 1.0), which doesn’t hold after scope/baseline changes. Option D (BAC/(CPI×SPI)) bakes schedule inefficiency into the cost forecast, appropriate when both cost and schedule trends will continue—again not true when a fresh plan replaces earlier patterns. A bottom-up ETC aligns EAC with new realities, improves credibility with stakeholders, and provides a sound basis for change control and re-baselining if approved.

Question 45

Which statement BEST differentiates Definition of Done (DoD) from acceptance criteria?

Correct answer: B

Explanation

The Definition of Done (DoD) is the commitment associated with the Increment—an agreed, organization- or product-level checklist that every completed item must satisfy (e.g., code reviewed, integrated, tests automated/passing, security checks, documentation updated). It ensures increments are usable and potentially releasable each sprint. Acceptance criteria are item-specific conditions that clarify scope and testability for a single Product Backlog Item (e.g., “Given/When/Then” scenarios). Meeting acceptance criteria alone isn’t sufficient if the item fails the DoD; conversely, an item may meet the DoD but not its acceptance criteria and therefore should not be accepted. Option A inverts the concepts. Option C is incorrect—while “Definition of Ready” is optional, DoD is fundamental to transparency and quality. Option D misassigns ownership; the Product Owner collaborates on acceptance criteria and value, Developers uphold the DoD, and the Scrum Master coaches the team in applying Scrum. Maintaining a clear DoD and precise acceptance criteria reduces rework, improves forecasting, and builds stakeholder trust.

Question 46

Which statement BEST describes the project charter?

Correct answer: B

Explanation

The project charter formally authorizes the project and grants the project manager authority to apply organizational resources to project activities. Typically issued by a sponsor or initiating entity, it summarizes the business need, high-level scope, key milestones, budget summary, stakeholders, and success criteria. It is not a detailed plan (Option A); the project management plan and its subsidiary plans define how the work will be executed and controlled. It is not a contract with the team (Option C), though it clarifies roles at a high level. Nor is it the Benefits Management Plan (Option D), which details how benefits will be tracked and realized post-delivery. For the CAPM, understanding the charter’s role during initiation is essential: it aligns expectations early, prevents scope drift by articulating objectives, and provides a reference for decision-making when trade-offs arise. The charter also catalyzes stakeholder identification and sets the stage for tailoring governance appropriate to the project’s complexity and risk profile.

Question 47

Which engineering practice most directly drives writing tests first to influence design and reduce defects?

Correct answer: C

Explanation

Test-Driven Development prescribes writing a failing automated test, implementing just enough code to pass it, and then refactoring while keeping tests green. This “red–green–refactor” loop promotes simpler, decoupled designs and creates a living regression suite that reduces defect escape. Pair programming (Option A) improves knowledge transfer and quality through continuous review, but it doesn’t mandate tests-first. Continuous integration (Option B) automates integration and quick feedback on changes but relies on tests already being present. Refactoring (Option D) improves internal code structure without altering behavior; it’s a companion to TDD but not a tests-first practice. CAPM’s agile domain highlights built-in quality and automation as enablers of potentially releasable increments each sprint. TDD supports a robust Definition of Done by embedding unit tests early, enabling safer change, and reducing rework costs later in the lifecycle. Combined with CI and code review, TDD increases maintainability and predictability.

Question 48

After strengthening the Definition of Done (adding integration and security tests), velocity dropped by ~20%. What is the BEST response?

Correct answer: B

Explanation

Velocity reflects the system of work and the team’s Definition of Done (DoD). When the DoD is strengthened, each story includes more work (e.g., integration, security testing), so velocity often decreases—but value and quality increase. The right response is to keep the improved DoD (built-in quality), be transparent about the new empirical capacity, and adjust forecasts and release plans accordingly. Reverting the DoD (Option A) trades short-term speed for long-term risk: technical debt, rework, and delayed defect discovery. Converting points to hours (Option C) doesn’t change throughput and reintroduces false precision. Increasing WIP (Option D) typically worsens cycle time and quality by creating bottlenecks. CAPM’s agile content emphasizes empiricism and flow: maintain a stable DoD, limit WIP, and use metrics like cumulative flow and lead time distributions to manage predictability. If stakeholders need earlier delivery, negotiate scope (re-slice stories thinner, defer lower-value items) or add capabilities (automation, pairing) that truly improve throughput without weakening quality.

Question 49

Which behavior is an anti-pattern for the Daily Scrum?

Correct answer: B

Explanation

The Daily Scrum is a short, team-owned planning event where Developers inspect progress toward the Sprint Goal and adapt their plan for the next 24 hours. It is not a status report to the Scrum Master. When the Scrum Master conducts a round-robin interrogation, it undermines self-management, shifts focus from outcomes to reporting, and can discourage collaborative planning. Correct practice centers on the work and the Sprint Goal: identify impediments, decide who will pair or swarm, and re-sequence tasks to finish items to the Definition of Done. The Scrum Master’s role is to ensure the event occurs, coach on effectiveness, and remove impediments identified—not to assign tasks or demand status. Visual boards, WIP limits, and concise coordination make the meeting outcome-oriented. This aligns with CAPM’s agile objectives of empiricism (transparency, inspection, adaptation) and flow (finish before starting more), leading to improved predictability and quality without ceremony bloat or command-and-control behaviors.

Question 50

You must compress the schedule without adding direct costs, accepting higher coordination risk instead. Which technique fits BEST?

Correct answer: B

Explanation

Fast tracking shortens the schedule by overlapping activities that were originally planned in sequence—often by introducing leads or converting some Finish-to-Start relationships to Start-to-Start. It does not inherently add cost, but it increases risk: rework due to incomplete predecessor information, additional defects, and more coordination effort. Crashing (Option A) also compresses the schedule but generally increases direct cost by applying more resources or premium options. Resource leveling (Option C) resolves over-allocation and can lengthen the schedule; it is not a compression technique. Rolling wave planning (Option D) is progressive elaboration, not schedule compression. CAPM-aligned practice: before fast tracking, ensure discretionary (soft) logic is identified, confirm the Definition of Done and acceptance criteria to limit rework, and update the risk register with secondary risks (integration errors, quality escapes). After introducing overlaps, re-run critical path analysis to detect new co-critical paths and monitor quality metrics closely. Communicate changes through integrated change control to maintain transparency with stakeholders and governance bodies.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free CAPM questions practiced · - overall accuracy

Want the full CAPM question bank?

Unlock all 268 questions with mock exam, explanations for every option and domain-level analytics.

Page 5 of 8 · Questions 41-50 of 80 free

PracticeTestMaster is an independent exam prep provider. CAPM is the property of PMI.

Full access

Unlock all 268 CAPM questions

You're practicing 80 free questions. Paid plans add:

  • 188 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your CAPM progress

Questions answered0
Accuracy-

Saved on this device.

CAPM exam overview

Exam
Certified Associate in Project Management
Code
CAPM
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 268 questionsFrom $19.99
Unlock