Skip to main content

Free CAPM Exam Questions That Helps Candidates Pass - Page 2

CAPM Questions 11-20 of 80 free
0/10 answered · 0 correct

Choose an answer and click Check answer to see if you're right, with the full explanation.

Question 11

Which statement about story points is MOST accurate?

Correct answer: B

Explanation

Story points are a relative measure of effort/complexity/risk compared to reference stories, not a direct time metric. Teams calibrate points using techniques like Planning Poker or bucket system, creating internal consistency that enables empirical forecasting via velocity (points completed per iteration). Option A misstates points as hours; conflating them with time undermines their benefit and invites false precision. Option C is incorrect—velocity uses points as-is; translating to hours reintroduces estimation bias. Option D misassigns the role: Developers estimate because they do the work, while the Product Owner prioritizes based on value, risk, and dependencies. CAPM’s agile coverage emphasizes empiricism: use historical velocity to forecast ranges, communicate uncertainty, and avoid fixed commitments too early. Points support conversations about scope and trade-offs, not contractual guarantees. Good practice includes maintaining a stable Definition of Done, refining large items into smaller, similarly sized stories, and revisiting estimates when significant learning occurs, thereby increasing predictability without over-engineering the estimation process.

Question 12

What is the PRIMARY purpose of the Sprint Review?

Correct answer: A

Explanation

The Sprint Review is a collaborative working session at the end of the sprint to inspect the increment and gather feedback from stakeholders. The goal is to adapt the Product Backlog based on what was built and what changed in the environment—market shifts, new risks, or emergent opportunities. The Review focuses on product outcomes, not team process. By contrast, the Sprint Retrospective (Option B) is for the team to inspect its process, relationships, tools, and Definition of Done, then identify improvement actions for the next sprint. Estimation and rebaselining (Option C) may occur during backlog refinement or release planning but are not the central purpose of the Review. Reassigning roles (Option D) isn’t a Review objective and can undermine team stability. CAPM’s agile domain stresses empirical process control: transparency, inspection, and adaptation. The Review operationalizes inspection/adaptation at the product level, helping maximize value delivery by validating assumptions early, mitigating risk, and ensuring that the backlog ordering reflects the most current understanding of stakeholder needs and business goals.

Question 13

Which quality tool helps prioritize categories of defects or causes by showing their relative frequency, often applying the 80/20 principle?

Correct answer: A

Explanation

A Pareto chart is a bar chart ordered from most to least frequent categories, typically with a cumulative percentage line to highlight the “vital few” categories contributing the majority of problems—an application of the Pareto (80/20) principle. It guides teams to focus improvement on the highest-impact areas first. A control chart (Option B) monitors process stability over time relative to control limits; it’s not used for categorical prioritization. A basic histogram (Option C) shows distributions but lacks the ordered bars and cumulative line that drive prioritization decisions. A scatter diagram (Option D) evaluates relationships between two variables, not categorical frequencies. CAPM quality management encourages using Pareto analysis in Manage Quality to target root-cause analysis and in Control Quality to monitor whether corrective actions reduce the dominant categories. Combined with cause-and-effect diagrams and 5 Whys, Pareto charts help allocate limited resources to the most consequential sources of defects, improving quality and cost performance.

Question 14

Which signal on a control chart MOST clearly indicates special-cause variation requiring investigation?

Correct answer: A

Explanation

A point outside control limits (typically ±3σ) is a classic, high-confidence indicator of special-cause variation—something changed beyond normal process noise—triggering investigation and corrective action. Patterns entirely within limits can also signal special causes (Western Electric rules), such as a run of many points on one side of the mean, trends of consecutive increases/decreases, or clustering in zones near limits; however, a single point beyond a control limit is the clearest, least ambiguous trigger. Random zig-zag (Option B) without rule violations generally reflects common-cause variation. Two near-limit points (Option C) may be suspicious, but by itself is not a definitive rule unless combined with additional points (e.g., 2 of 3 in zone A). Mild drift around the mean (Option D) may be normal unless it forms a defined trend rule. CAPM quality control stresses distinguishing process control (common causes) from capability (meeting specs). After detecting special cause, teams should identify root causes, implement corrective actions, and then monitor to confirm the process returns to statistical control.

Question 15

Mid-sprint, the Product Owner requests adding a new high-priority item. What is the BEST action?

Correct answer: C

Explanation

Scrum balances flexibility with focus. During a sprint, scope may be clarified and the Product Owner and Developers can re-negotiate items as more is learned—provided the Sprint Goal remains achievable. If the new item threatens the goal, the appropriate action is to keep it in the Product Backlog for future selection or, in rare cases, the Product Owner may cancel the sprint if the goal has become obsolete. Automatically adding items (Option A) undermines focus and predictability. Blanket refusal (Option D) ignores Scrum’s allowance for collaborative re-negotiation. Immediate cancellation (Option B) is a last resort and wastes work-in-progress unless the goal is no longer valid. CAPM agile objectives underscore maintaining a stable Definition of Done, transparent backlogs, and empirical forecasting. The team should assess impact, consider trading out equivalent work, and update stakeholders. This approach protects flow and quality while remaining responsive to emergent value, preserving trust and cadence.

Question 16

You must describe goal-level interactions between an actor and a system, with basic flows, alternates, and pre/post-conditions (not UI layout). Which technique fits BEST?

Correct answer: B

Explanation

Use cases capture how an actor achieves a goal with the system through a main success path and alternate/exception flows, framed by preconditions and postconditions. They are ideal when you need structured, testable narratives that clarify scope boundaries without prescribing UI. User stories (A) are concise placeholders for conversation and acceptance criteria; they rarely convey end-to-end flow by themselves. Story mapping (C) visualizes the user journey and helps slice releases but is higher level. Wireframes (D) focus on interface layout, not underlying interaction logic. CAPM-aligned analysis stresses selecting the artifact that reduces the most ambiguity for the audience. Well-formed use cases complement a data dictionary and sequence diagrams: together they define behavior, terminology, and message timing. They also feed the Requirements Traceability Matrix and test design (deriving cases for each alternate/exception flow). Keeping use cases technology-agnostic enables flexibility during design while preserving verifiable outcomes for validation and acceptance.

Question 17

Which statement BEST contrasts CPM and PERT in schedule development?

Correct answer: C

Explanation

Critical Path Method (CPM) commonly applies single-point deterministic activity durations to build the network, determine early/late dates, and identify the path with zero total float. Program Evaluation and Review Technique (PERT) models uncertainty with three-point estimates using a weighted average (often (O + 4M + P)/6) to derive expected durations and sometimes variance. While modern tools blend approaches, conceptually PERT emphasizes stochastic modeling of time risk, whereas CPM emphasizes deterministic planning and critical path analysis. Option A reverses roles. Option B misstates CPM’s focus; resource leveling is a separate process that can be applied to any network. Option D is a false specialization; both techniques are domain-agnostic. CAPM candidates should also understand that once expected durations are calculated (PERT), the resulting network can be analyzed similarly to CPM. Further, teams may perform quantitative schedule risk analysis (e.g., Monte Carlo) on the network to generate probabilistic completion dates and confidence levels for milestones.

Question 18

Which statement BEST describes a Directive PMO?

Correct answer: C

Explanation

PMOs vary in authority. A Directive PMO exerts the highest level: it supplies project managers, owns standards, and directly manages projects, often in organizations seeking consistency and strong governance. A Controlling PMO (Option B) enforces compliance via frameworks, tools, and audits but typically leaves day-to-day management to functional/line PMs. A Supportive PMO (Option A) is consultative—offering templates, best practices, and mentoring with low control. Option D ignores the governance role PMOs play. CAPM fundamentals emphasize tailoring PMO structures to organizational maturity and strategy. Directive PMOs can improve outcomes through consistent practices and centralized oversight but must balance control with agility, avoiding bureaucratic delay. Clear charters, defined decision rights, and service catalogs help stakeholders understand how the PMO engages (e.g., portfolio prioritization, resource brokering, coaching). Measuring PMO value through delivery performance and benefits realization maintains executive sponsorship and continuous improvement.

Question 19

In Critical Chain Project Management (CCPM), which buffer primarily protects the overall project completion date from variability on the longest chain of dependent tasks?

Correct answer: B

Explanation

Critical Chain focuses on resource constraints and variability by protecting the delivery date with time buffers rather than padding each activity. The project buffer is placed at the end of the critical chain—i.e., after the last task in the longest sequence considering resource dependencies. Its purpose is to absorb aggregate variance so that delays in upstream activities do not slip the committed finish date. Feeding buffers (Option A) are inserted where noncritical chains feed into the critical chain; they protect the critical chain from upstream slippage on those paths. Resource buffers (Option C) are alerts or flags positioned ahead of tasks that require critical resources to ensure availability and timely start, not extra time added to duration. Management reserve (Option D) is governance-held contingency outside baselines, not a scheduling mechanism inside the network model. CAPM candidates should recognize that CCPM reduces multitasking, uses aggressive but achievable task durations, and tracks buffer consumption as a leading indicator. When buffer burn is faster than planned, managers take action—resequence, remove impediments, or add focused support—before the final date is threatened.

Question 20

Which statement about Definition of Done (DoD) and acceptance criteria is MOST accurate?

Correct answer: A

Explanation

In agile practices, the Definition of Done (DoD) is a shared, transparent quality bar that applies to every increment; it often includes coding standards, peer reviews, automated tests, integration, documentation, and compliance steps required for a potentially shippable increment. It is typically established by the team (and may incorporate organizational standards) to ensure consistency and transparency of quality. Acceptance criteria, by contrast, are specific to an individual backlog item (e.g., a user story) and describe functional and sometimes nonfunctional conditions that must be satisfied for that item to be accepted by the Product Owner. Option B reverses the nature of these concepts. Option C improperly narrows DoD to testing only; DoD spans all work necessary to consider an increment complete. Option D misstates accountabilities; the DoD is not dictated unilaterally by the Product Owner—teams collaborate to set and evolve it. CAPM’s agile domain stresses clear quality definitions and validation practices to reduce ambiguity, prevent partial completion, and enable predictable velocity by ensuring that “done” means “releasable,” not merely “coded.”

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free CAPM questions practiced · - overall accuracy

Want the full CAPM question bank?

Unlock all 268 questions with mock exam, explanations for every option and domain-level analytics.

Page 2 of 8 · Questions 11-20 of 80 free

PracticeTestMaster is an independent exam prep provider. CAPM is the property of PMI.

Full access

Unlock all 268 CAPM questions

You're practicing 80 free questions. Paid plans add:

  • 188 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your CAPM progress

Questions answered0
Accuracy-

Saved on this device.

CAPM exam overview

Exam
Certified Associate in Project Management
Code
CAPM
Category
Professional
Credential body
PMI
Updated
Nov 24, 2026
Unlock all 268 questionsFrom $19.99
Unlock