Question # 56

After the kickoff charrette, what is the most integrative, low-cost way to keep decisions evidence-based through schematic design?

Options:

A.

Pause analysis until CDs to avoid rework

B.

Run quick “shoebox” energy studies and a preliminary water balance each week; update OPR/BOD and specs with targets; have the CxA verify at milestone check-ins

C.

Let vendors propose substitutions at bid time for savings

D.

Focus only on HVAC efficiencies and revisit envelope later

Question # 57

On a newly registered project, team members are unsure who manages access, deadlines, and formal submissions in LEED Online. Which role is primarily responsible?

Options:

A.

Sustainability consultant (any team member)

B.

Project Administrator designated in LEED Online

C.

Mechanical engineer of record

D.

Local USGBC community chair

Question # 58

A private office with limited visitor hours wants ongoing public education with minimal staff time. What program is most durable?

Options:

A.

One-time press release and a plaque

B.

Durable interpretive signage at visible features (e.g., rain garden, PV), QR codes to short plain-language pages with periodic updates, and a small lobby display of high-level energy/water trends

C.

Technical dashboards on every floor for visitors

D.

Tours by appointment only with no self-guided materials

Question # 59

At project start, the team asks how to scope the Site Assessment to guide better decisions. What should it include?

Options:

A.

A brief note that “site is urban” with no data

B.

A documented analysis of climate, soils and hydrology, existing vegetation/habitat, transportation/connectivity, and surrounding uses, with maps/photos and key opportunities/constraints

C.

Only a cost estimate for landscaping

D.

A planting palette selected before any site analysis

Question # 60

After the discovery workshop, the team identified an envelope + daylight + controls package that holds energy use flat while allowing a smaller mechanical system. How should they keep this synergy intact through VE and bidding?

Options:

A.

Treat results as advisory and let bidders value-engineer freely

B.

Convert performance targets into enforceable specs (enclosure airtightness/thermal continuity, glazing/shading, LPD and continuous dimming), add required metering/trend points and sequences, and have the CxA police compliance at milestones

C.

Rely on a post-occupancy “tuning” budget to correct any drift

D.

Ask vendors to propose “equal” products based on lowest first cost

Viewing question 12 out of 15 questions


Go to LEED Green Associate Exam Main Page

Don't just take our word for it. Industry research shows that targeted LEED Green Associate practice test dramatically increases pass rates for the LEED Green Associate. Our platform is built on this principle, offering the most realistic simulations available to give you that proven advantage.


LEED Green Associate Overview

Name LEED Green Associate
Code LEED Green Associate
Vendor Professional
Certification USGBC

Our free LEED Green Associate exam questions are your personalized diagnostic tool. Get an instant, honest snapshot of your readiness for the LEED Green Associate certification exam and identify the specific topics that need your focus.

LEED Green Associate Questions

What You Get with Full Access:

Complete Questions Bank

Timed Exam Simulator

Smart Performance Dashboard

Identify Weak Spots

Verified Answer & Explanations

Unlimited Reattempts

Mobile-Friendly Study

Regular Content Updates



1 Month Access

$19.99

Buy Now


12 Months Access

$49.99

Buy Now

LEED Green Associate Complete Package

Choose a plan and prepare with realistic LEED Green Associate practice exam designed to mirror test-day conditions. Every plan includes a full LEED Green Associate question bank, a timed exam simulator, performance tracking, detailed answer explanations, and the ability to reattempt questions to improve accuracy and confidence.

284 Practice Questions - Flexible Quiz Modes - Unlimited Attempts