Skip to main content

Free LARE Exam Questions That Helps Candidates Pass - Page 7

LARE Questions 61-70 of 80 free
0/10 answered · 0 correct

Choose an answer and click Check answer to see if you're right, with the full explanation.

Question 61

You are asked to prepare a cost estimate early in schematic design. Which type of estimate is most appropriate?

Correct answer: B

Explanation

In schematic design, only general program and layout information is available. A square-foot or unit-area cost estimate based on historical benchmarks and similar projects is most appropriate. This approach provides clients with an order-of-magnitude understanding of costs without the precision of full takeoffs. Option A (detailed takeoff) belongs to design development or construction documents when specifications and dimensions are finalized. Option C (GMP) is negotiated later, typically after DD or CDs. Option D (contractor bids) occur at the bidding stage, not schematic design. Using benchmark-based estimates aligns with project management best practices, allowing informed scope adjustments early without overspending effort.

Question 62

A contractor proposes a substitution for specified concrete unit pavers due to long lead times. What is the most appropriate response during submittal review?

Correct answer: C

Explanation

Construction administration requires impartial evaluation of proposed substitutions in accordance with Division 01 and the technical sections. The reviewer should assess durability (compressive strength, freeze-thaw resistance), dimensional tolerances, surface texture, color range, slip resistance, and compatibility with bedding/sand joints. Installation method, pattern, and jointing must meet the design intent and performance criteria, including permeable vs. impermeable systems. Maintenance requirements, warranty terms, and lifecycle costs are also relevant. A field mockup allows verification of color blend and craftsmanship, serving as the quality benchmark. Automatically rejecting substitutions (Option A) may be impractical and can conflict with contract provisions. Approving solely on price (Option B) neglects performance and aesthetics. Deferring to contractor preference (Option D) abdicates the designer’s responsibility to protect the owner’s interests and maintain design intent. A structured equivalency review ensures that any change preserves quality and project objectives.

Question 63

Which grading solution best ensures ADA accessibility on sloped sites?

Correct answer: A

Explanation

ADA-compliant walkways maintain ≤5% longitudinal slopes where feasible; if steeper, treat as ramps with landings and handrails. Cross-slopes must not exceed 2%. Slopes greater than 4% crosswise (Option B) hinder accessibility. Turf paths (Option C) lack stability. Stairs (Option D) exclude mobility-impaired users. Accessibility through careful grading is a fundamental responsibility of landscape architects, emphasized in L.A.R.E. Section 4.

Question 64

Which project management tool assigns accountability and tracks task ownership?

Correct answer: A

Explanation

A RACI matrix designates who is Responsible, Accountable, Consulted, and Informed for each task, clarifying roles and preventing conflicts. Gantt charts (Option B) manage schedules. Site plans (Option C) and environmental assessments (Option D) focus on design or environmental conditions, not accountability. RACI matrices are emphasized in Inventory and Analysis under L.A.R.E. project management knowledge.

Question 65

Which feature most encourages year-round use of a public square in a temperate climate?

Correct answer: A

Explanation

Year-round usability requires climate-responsive design. Shade structures and trees mitigate heat in summer; windbreaks and sheltered seating improve winter comfort. Flexible seating supports both small gatherings and large events. A single seasonal use (Option B) underutilizes the space. Exposed concrete (Option C) increases heat and discomfort. Perimeter-only seating (Option D) reduces engagement with central activity. Designing for all-season adaptability aligns with L.A.R.E. Planning and Design principles of inclusivity and resilience.

Question 66

Which design measure most effectively controls erosion along streambanks?

Correct answer: A

Explanation

Streambank stabilization using bioengineering—live stakes, coir rolls, fascines—reinforces banks while maintaining habitat. Bare soil (Option B) erodes quickly. Concrete lining (Option C) increases velocity and degrades ecology. Concentrated runoff (Option D) worsens erosion. Bioengineering blends ecological function with engineering, a best practice emphasized in L.A.R.E. Section 4.

Question 67

Which design feature best supports universal accessibility in a playground?

Correct answer: B

Explanation

Inclusive playgrounds integrate ramps, transfer stations, and ground-level features so all children play together. Stairs-only access (Option A) excludes users. Turf-only paths (Option C) are unstable and noncompliant. Separate entries (Option D) stigmatize users. Universal design emphasizes dignity and integration, aligning with Planning and Design objectives emphasized on the L.A.R.E. exam.

Question 68

Which document formally tracks contractor-provided product data, shop drawings, and samples throughout review and approval?

Correct answer: A

Explanation

The submittal log tracks each item required for review, documenting submission, review, approval, and resubmittals. Addenda (Option B) are pre-bid modifications. Punch lists (Option C) identify deficiencies at closeout. Change orders (Option D) alter scope, time, or cost. Submittal tracking ensures contract compliance and quality assurance, a key Construction Documentation and Administration duty in the L.A.R.E.

Question 69

When sizing stormwater pipes, what is the primary design consideration?

Correct answer: B

Explanation

Pipe sizing is based on peak flow from hydrologic analysis (e.g., Rational Method, NRCS TR-55), pipe slope, and roughness coefficients (Manning’s equation). This ensures adequate conveyance without surcharge or erosion. Contractor preference (Option A) and planting palettes (Option C) do not determine pipe hydraulics. Furnishings (Option D) are unrelated. Correct pipe sizing safeguards public safety, complies with stormwater codes, and reflects applied hydrology knowledge required by the L.A.R.E. Section 4 exam.

Question 70

Which specification type describes the required results but not the methods?

Correct answer: A

Explanation

Performance specifications state outcomes (e.g., pavement must support a certain load) but allow contractors to propose compliant methods. Descriptive (Option B) prescribes materials and installation. Proprietary (Option C) names specific products. Reference standards (Option D) cite third-party standards. Performance specifications encourage innovation while ensuring outcomes, key in Construction Documentation and Administration knowledge in L.A.R.E.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free LARE questions practiced · - overall accuracy

Want the full LARE question bank?

Unlock all 241 questions with mock exam, explanations for every option and domain-level analytics.

Page 7 of 8 · Questions 61-70 of 80 free

PracticeTestMaster is an independent exam prep provider. LARE is the property of Council of Landscape Architectural Registration Boards (CLARB).

Full access

Unlock all 241 LARE questions

You're practicing 80 free questions. Paid plans add:

  • 161 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your LARE progress

Questions answered0
Accuracy-

Saved on this device.

LARE exam overview

Exam
Landscape Architect Registration
Code
LARE
Credential body
Council of Landscape Architectural Registration Boards (CLARB)
Updated
Nov 24, 2026
Unlock all 241 questionsFrom $19.99
Unlock