Question 61
You are asked to prepare a cost estimate early in schematic design. Which type of estimate is most appropriate?
Explanation
In schematic design, only general program and layout information is available. A square-foot or unit-area cost estimate based on historical benchmarks and similar projects is most appropriate. This approach provides clients with an order-of-magnitude understanding of costs without the precision of full takeoffs. Option A (detailed takeoff) belongs to design development or construction documents when specifications and dimensions are finalized. Option C (GMP) is negotiated later, typically after DD or CDs. Option D (contractor bids) occur at the bidding stage, not schematic design. Using benchmark-based estimates aligns with project management best practices, allowing informed scope adjustments early without overspending effort.