Question 21
Which document authorizes a contractor to proceed with extra work before finalizing a change order?
Explanation
A Construction Change Directive (CCD) directs the contractor to perform work immediately while cost and time adjustments are negotiated. Addenda (Option B) modify bidding documents pre-contract. Punch lists (Option C) record deficiencies. Submittals (Option D) provide product data. CCDs ensure work progresses without delay, critical in Construction Documentation and Administration knowledge for the L.A.R.E.