Question 51
Which scenario indicates that an ESWC has not been properly established?
Explanation
Skipping the final live verification step undermines the process. Even if zero voltage is shown, a faulty meter may have masked the true hazard. Option A, B, and D represent correct practice. ASE Level 2 emphasizes completing the full live-dead-live cycle to ensure both system and equipment integrity. Any missing step means an ESWC has not been fully achieved, exposing technicians to serious risk.