Journey Level Plumber Questions 61-70 of 90 free
0/10 answered · 0 correct

Choose an answer and click Check answer to see if you're right, with the full explanation.

Question 61

Copper tubing for water supply is joined using:

Correct answer: B

Explanation

Comprehensive and Detailed Explanation:

IPC Section 605 requires approved methods for copper joints, typically soldered with lead-free alloy. Flux and cleaning are critical. Westchester installations must use listed materials. Exams test joint types. Proper technique prevents leaks.

Question 62

Threaded joints in copper piping for water are made using:

Correct answer: B

Explanation

Comprehensive and Detailed Explanation:

IPC approves mechanical methods for copper. Ensures leak-free connections.

Question 63

Combustion air for gas water heaters must be provided:

Correct answer: B

Explanation

Comprehensive and Detailed Explanation:

IPC Chapter 5 prevents incomplete combustion.

Question 64

A 4-inch stack can carry a maximum of how many DFU at typical loads?

Correct answer: B

Explanation

Comprehensive and Detailed Explanation:

IPC tables provide stack capacities based on DFU and venting. Proper design prevents overload.

Question 65

The minimum size of a cleanout for a 4-inch pipe is:

Correct answer: D

Explanation

Comprehensive and Detailed Explanation:

IPC Section 708 provides maintenance access.

Question 66

Secondary roof drainage systems must be sized to:

Correct answer: B

Explanation

Comprehensive and Detailed Explanation:

IPC Section 1101 requires overflow protection to prevent structural failure. Independent discharge paths are mandatory. Critical in Westchester weather conditions.

Question 67

The maximum developed length of vent piping is determined by:

Correct answer: B

Explanation

Comprehensive and Detailed Explanation:

Table 906.1 governs vent lengths. Ensures adequate airflow. Critical for system design.

Question 68

The minimum cross-sectional area for a shower receptor is:

Correct answer: B

Explanation

Comprehensive and Detailed Explanation:

IPC Section 421.4 requires 900 square inches and space for a 30-inch circle. Ensures usability and drainage.

Question 69

Leaders inside buildings must be:

Correct answer: B

Explanation

Comprehensive and Detailed Explanation:

IPC Chapter 11 addresses materials and protection. Coordinates with building code.

Question 70

The maximum allowable velocity in copper water piping is generally:

Correct answer: B

Explanation

Comprehensive and Detailed Explanation:

IPC guidelines and standards recommend velocities not exceeding 8 fps in copper tubing to minimize erosion and noise. Sizing calculations use WSFU tables. Westchester plumbers balance flow and pressure. This prevents premature wear. Key for system design exams.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 90 free Journey Level Plumber questions practiced · - overall accuracy

Want the full Journey Level Plumber question bank?

Unlock all 300 questions with mock exam, explanations for every option and domain-level analytics.

Page 7 of 9 · Questions 61-70 of 90 free

PracticeTestMaster is an independent exam prep provider. Journey Level Plumber is the property of NITC.

Full access

Unlock all 300 Journey Level Plumber questions

You're practicing 90 free questions. Paid plans add:

  • 210 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your Journey Level Plumber progress

Questions answered0
Accuracy-

Saved on this device.

Journey Level Plumber exam overview

Exam
Journey Level Plumber
Code
Journey Level Plumber
Credential body
NITC
Updated
Nov 24, 2026
Unlock all 300 questionsFrom $19.99
Unlock