Question 61
Which document lists outstanding items requiring correction before project completion?
Explanation
A punch list identifies deficiencies and incomplete work at project closeout. Contractors correct items before final acceptance. Change orders adjust contracts, addenda modify pre-bid documents, and proposals define initial scope. The punch list is critical for ensuring quality completion.