Question 31

What is the purpose of a bid bond?

Correct answer: B

Explanation

A bid bond guarantees that the contractor will accept the job at the bid price if selected. If not, the bond compensates the owner. Payment bonds (A) ensure subcontractor payment, while insurance (D) is separate. Bid bonds protect public and private owners from non-committed bidders.

Question 32

Which method combines cost, scope, and schedule to measure project performance?

Correct answer: A

Explanation

Earned Value Management (EVM) integrates cost, scope, and schedule to provide a complete picture of project performance. It highlights cost variances and schedule delays early. CPM (B) focuses on scheduling only, takeoff (C) on estimating, and retainage (D) on finances.

Question 33

What does a “competent person” on a construction site have the authority to do?

Correct answer: B

Explanation

A competent person is defined by OSHA as someone with the knowledge to identify hazards and the authority to correct them. This is a critical role in site safety compliance.

Question 34

What is the purpose of a certificate of occupancy?

Correct answer: B

Explanation

A certificate of occupancy is issued by the local building official to certify that a completed building meets code and is safe for occupancy. It is required before owners or tenants can use the building. It does not authorize bidding (A) or licensing (C). Safety training (D) is separate. Compliance ensures safe, code-approved structures.

Question 35

What is the minimum number of apprentices a contractor must employ on California public works projects?

Correct answer: B

Explanation

California requires contractors on public works projects to employ 1 apprentice for every 5 journeymen in applicable trades. This promotes workforce development and compliance with apprenticeship laws.

Question 36

Which document is used to make a minor change in project scope without affecting contract price or time?

Correct answer: B

Explanation

A field order is used for minor changes that do not impact cost or time. A change order (C) modifies cost or schedule. Addenda (A) are pre-contract clarifications, and bonds (D) secure financial obligations. Contract management best practice includes documenting all changes, major or minor.

Question 37

Which party does a payment bond primarily protect?

Correct answer: C

Explanation

A payment bond ensures subcontractors and suppliers receive payment, even if the general contractor defaults. Performance bonds (A) protect owners, while license bonds protect the public.

Question 38

Which document provides the contractor with formal permission to begin construction?

Correct answer: B

Explanation

A Notice to Proceed (NTP) is issued by the owner to authorize the contractor to begin work according to contract terms. It differs from permits and occupancy certificates.

Question 39

Which document summarizes a contractor’s revenues and expenses for a given period?

Correct answer: B

Explanation

The income statement (profit and loss statement) shows revenues, expenses, and net income for a specific period. The balance sheet (A) shows position at one time, and cash flow (C) tracks liquidity.

Question 40

When is a down payment legally limited to 10% of the contract price or $1,000, whichever is less?

Correct answer: C

Explanation

In California, for residential home improvement contracts, the maximum down payment a contractor may legally collect is 10% of the contract price or $1,000, whichever is less. This law protects homeowners from financial risk if the contractor fails to perform. Commercial projects and public works are not subject to this rule. Contracts under $500 are exempt from CSLB requirements. This safeguard is a critical part of consumer protection laws.

0%

Your score on this page: 0/0

Answer the questions above to see your score.

0 of 80 free General Contractor License questions practiced · - overall accuracy

Want the full General Contractor License question bank?

Unlock all 258 questions with mock exam, explanations for every option and domain-level analytics.

Page 4 of 8 · Questions 31-40 of 80 free

PracticeTestMaster is an independent exam prep provider. General Contractor License is the property of State Licensing Boards.

Full access

Unlock all 258 General Contractor License questions

You're practicing 80 free questions. Paid plans add:

  • 178 more exam-style questions
  • Timed mock exam simulations
  • Domain-level score analytics
  • Unlimited reattempts
1 Month $19.99
Buy
12 Months $49.99
Buy
See everything included

Your General Contractor License progress

Questions answered0
Accuracy-

Saved on this device.

General Contractor License exam overview

Exam
General Contractor License
Code
General Contractor License
Credential body
State Licensing Boards
Updated
Nov 24, 2026
Unlock all 258 questionsFrom $19.99
Unlock